<br />a <br />EXHIBIT B.2 <br />ESTIMATED SCHEDULE OF SERVICES <br />* The schedule for Phase I services is anticipated as <br />follows: <br />* Relocation Plan NTP + 5 Mos. <br />* Land Acquisition Cost Estimates NTP + 5 Mos. <br />* Draft EIAR NTP + 6 Mos. <br />* Preliminary Engineering Report/ <br /> Preapp. Support NTP + 6 Mos. <br />* Public Hearing NTP + 7 Mos. <br />* Final EIAR NTP + 9 Mos. <br /> (dependent on agency review) <br />The intent of the Phase I schedule is to submit a preapplication <br />for FY 1988 AIP funding by September 30, 1987. This schedule date may <br />vary dependent on funding participation and Notice to Proceed (NTP). <br />7 <br />