UPDATE ON TRUNK HIGHWAY #47 <br /> By: Steve Jankowski, City Engineer <br /> <br />P. W CASE #: <br /> <br />Background: <br /> <br />At the July 11, 2000 City Council meeting staff reported on two issues concerning the <br />construction project on the Trunk Highway #47. This case is meant to provide the most <br />current update on those two issues. You will recall one issue involved Great Rivers <br />Energy and U.S West both of which had utilities located near 153~d Avenue N.W. and <br />Trunk Highway #47. These companies both had easements for their facilities to be in <br />their present locations. At the time of this writing the situation is as follows. Great <br />Rivers Energy has delivered-a wooden power pole to the site and I have been advised <br />installation is scheduled for Tuesday, July 18, 2000. Attached is a letter agreement the <br />City received from Great Rivers Energy to move the power pole at the cost of <br />$15,693.95. <br /> <br />I have also received a phone call from Quest (formerly known as U.S West) advising me <br />that the cost to relocate the utility cabinet is $11,132.23. The previously stated estimated <br />cost of moving this cabinet was $35,000. I have been advised by the field representative <br />from U.S West at the weekly construction meeting that U.S West would not move the <br />existing cabinet until both a recorded easement and a signed agreement was in their <br />hands. I have delivered the easement to the City Attorney for recording at the time of this <br />writing. <br /> <br />The second issue discussed at the July 11, 2000, City Council meeting concerned the <br />closure of Trunk Highway #47 north of County Road 5. Attached is a map showing the <br />area of the roadway that would be closed and available alternative routes during the two <br />week closure period. I am also enclosing a draft letter that will be sent to the residents <br />within the notification area advising them of this phasing change to the Trunk Highway <br />#47 project. Secondly I was asked to discuss with the contractor a reduction in cost of <br />the project in for providing the closure. I have made contact with the contractor and will <br />report on his response at the meeting. <br /> <br />Committee Action: <br /> <br />Based upon discussion. <br /> <br />Review by: <br />City Administrator <br />Public Works Director <br /> <br />P.W. 07/18/00 <br /> <br /> <br />