TH #47 STP PROJECT
<br />COST ESTIMATE
<br />
<br />February12,1998
<br />
<br />Item Federal State County City Total
<br />Construction Cost 2,280,000 381,250 188,750 0 2,850,000
<br />Engineering/Inspection 32,000 37,750 500,250 570,000
<br />Right-of-Way/Land 1'8,750 28,300 -1,952,950 2,000,000
<br />Total' 2,280,000 432,000 254,800 2,453,200 5,420,000
<br />
<br />October 14, 1999
<br />
<br />Item Federal State County City Total
<br />Construction Co~t 2,663,300 500,000 250,000 35,823 3,449,123
<br />Engineering/Inspection 0 0 580,163 580,163
<br />Right-of-Way/Land 0 0 2,162,800 2,162,800
<br />Total 2,663,300 500,000 250,000 2,778,786 6,192,086
<br />
<br />Difference +383,300 +68,000 -4,800 +325,586 +772,086
<br />
<br />Total expended by City as of October 14, 1999 is $2,204,439.