The estimated delivery time on the pump and VFD is 3 weeks, and 2 weeks are required for <br />installation. In order to make these improvements prior to the high demand season, it is <br />suggested that the work be separated into parts done by different type contractors. For example, <br />quotations could be obtained for the well pump and separate quotations for the electrical work. <br />Authorization to proceed must be given quickly after quotes are received. <br />We would be happy to discuss any of these recommendations with you. <br />Sincerely, <br />BONESTROO, ROSENE, ANDERLIK & ASSOCIATES, INC. <br />/®r �-; � <br />Richard W. Foster <br />RWF:gs <br />1q <br />