f <br />f <br />by the assessment anticipated. It is estimated that $7,085 of the project cost is <br />' attributable to oversiiing of the watermain and sanitary sewer and will be financed <br />from the City's sewerland water trunk fund. In addition, $16,718 will be contributed <br />t to the street and sidewalk construction of Xkimo Street NW to meet MSA standards. <br />This amount will be recovered from the State as an MSA project. <br />' SCHEDULE <br />For this project to prdceed the following schedule could be anticipated: <br />1 i <br />Accept feasibility study and set public hearing June 13, 1995 <br />' Hold public hearing and authorize plans and specifications June 27, 1995 <br />Authorize bidding July 11, 1995 <br />Receive bids Od award August 8, 1995 <br />' Begin construction August 21, 1995 <br />Complete construction Late September, 1995 <br />Hold assessment hearing September, 1995 <br />' First payments fdue ' May, 1996 <br />i <br />i <br />4 <br />