CC Regular Session <br />Meeting Date: 06/26/2012 <br />By: Tim Himmer, Engineering/Public <br />Works <br />Information <br />Title: <br />Consider Award of Contract for City Improvement Project 12-20; Sunwood Drive Realignment <br />7. 6. <br />Background: <br />The Armstrong Boulevard/Highway 10 interchange project is considered one of the highest transportation priorities <br />in the City. In an effort to reduce the overall costs the Council has been discussing ways to preconstruct portions of <br />this project, such that it can be accomplished in phases. One phase of this interchange project is the realignment of <br />Sunwood Drive, which is being considered to improve traffic flow through the area in the short term, create a <br />consolidated signalized access to the COR along its western boundary, provide for a portion of the City's cost <br />participation in the interchange project, and create additional development options for the COR property. The <br />Sunwood realignment will construct the first intersection north of Highway 10 on Armstrong Boulevard, at a <br />location that addresses the major concerns expressed by MnDOT and Anoka County. <br />The project includes the realignment of Sunwood Drive, between approximately Zeolite Street and Armstrong <br />Boulevard (see attached preliminary design). The intent is to work north to south on Armstrong Boulevard and <br />complete another section of the roadway in its final location; to set the stage for the ultimate interchange over the <br />railroad tracks and Highway 10. Draft feasibility studies were presented to the Public Works Committee and HRA <br />on December 13, 2011, and on that date the HRA authorized the preparation of appraisals for the potential <br />acquisition of 3 parcels along the west side of Armstrong Boulevard that are necessary for portions of this project, <br />and ultimately the interchange project. <br />On January 24, 2012, draft feasibility studies were presented to the City Council for consideration. At that meeting <br />the City Council authorized the final design contracts with Landform and WSB & Associates, and ordered the <br />preparation of plans and specifications. On May 22, 2012, the City Council authorized the bidding of the Sunwood <br />project. On June 12, 2012, the City Attorney and staff updated the Council on the required acquisitions for the <br />project, and provided an updated project accounting. It was the direction from that meeting to continue with the <br />land acquisitions, as they would be necessary for the interchange project, and come back with a final funding <br />package once the bids for the project are opened and award of a construction contract is being considered. To date <br />all properties needed for this project have been negotiated and tentative deals are in place. <br />Observations: <br />The final plans and specifications have been submitted to and approved by the various review agencies, including <br />Anoka County and the Minnesota Department of Transportation (MnDOT). It is required that we have final <br />approval from both entities before the bids can be opened and a contract awarded. The plans and specifications <br />were published according to State Statutes and distributed to various contractors. The bids were opened on <br />Monday June 25th, tabulated, reviewed, and forwarded to the City Council (along with a final financing package) <br />prior to the June 26th meeting where an award of a construction contract is being considered. This agenda has now <br />been updated with the bid information. <br />Recommendation: <br />Staff recommends that the City Council approve Resolution 12-06-XXX, awarding a contract for City <br />Improvement Project 12-20; Sunwood Drive Realignment, to North Pine Aggregate, Inc., in the amount of <br />$2,342,825.82. The contractor and cost information are attached. The accompanying resolution) will be updated <br />following the award of bid by Council and prior to execution. <br />