MnDOT Contract No. 02010 <br />EXHIBIT B <br />PROJECT COMPLETION SCHEDULE <br />(Provide for enough time to final the project through the MnDOT state aid pay request process.) <br />July 13,2012 Install Silt Fence/ Clearing in Sunwood Drive Area <br />July 16, 2012 Begin sewer and water connections along Sunwood Drive <br />July 16, 2012 to August 3, 2012 Stage 1 — Construct Zeolite Street and 147th Ave Widening <br />August 6, 2012 to Sept. 7, 2012 Stage 2 — Construct Sunwood Drive, Raise Armstrong Blvd <br />Form existing centerline of Sunwood Drive to the north <br />Sept. 10, 2012 to Oct 5, 2012 <br />Stages 3A &3B — Construct Sunwood Drive connections <br />and removal of existing Sunwood Drive <br />Oct. 8, 2012 to Oct. 31, 2012 Stage 4 — Construct last leg of Armstrong Boulevard <br />May 15, 2013 Project Closeout <br />June 2013 Request Final Payment <br />4 <br />