A bidder may submit a bid on any number of Bid Categories listed below. A separate bid must be submitted on
<br />a lump sum basis for each Bid Category listed. For example, if bidding on three categories, a bidder submits
<br />three individual sealed bids. Partial bids will not be accepted.
<br />CONSTRUCTION MANAGER SHALL PROVIDE FOR ALL SUBCONTRACTOR USE - General building
<br />permit, special inspections, testing, temporary sanitary facilities, waste disposal containers, ground snow
<br />removal, temporary construction entrance, construction water source, office trailer, survey layout of
<br />foundations and elevation, temporary heat after building is enclosed.
<br />ALL SUBCONTRACT (S) TRADES SHALL PROVIDE — Drinking water, daily clean-up, waste removal to roll
<br />off container, permits, fees and licensing if required, secure material storage, extension cords and all
<br />necessary tools and equipment for a complete installation, roof and floor snow removal, temporary heat and
<br />cover until building is enclosed for your work.
<br />MATERIALS ONLY BIDS (M) — Shall include field measuring prior to fabrication, delivery to jobsite, 7.275%
<br />sales tax, material returns for unused material at 100% credit and free pick up or shipping.
<br />Bid package No. 1 includes twenty-seven (27) bid categories. They are as follows:
<br />02300 EARTHWORK (S) — Includes perimeter silt fence, catch basin protection, stripping sod and dispose of
<br />offsite, strip and stockpiling topsoil (protect stockpile), cut and fill to subgrade, foundation excavation, backfill
<br />and compaction, import and place 6" sand cushion for floor slabs, exterior slabs and sidewalks, F & 110 mil
<br />vapor barrier, final grade topsoil to 6" depth minimum at +/- 1/10", remove excess soils from site.
<br />02500 UTILITIES (S) — Includes connect water line to existing waterline, provide curb stop, install waterline into
<br />building mechanical room and provide valve, disinfect, test for bacteria. Connect sanitary sewer from building
<br />foundation wall to drainfield connection. Underground bore beneath existing parking lot.
<br />02600 SEPTIC SYSTEM (S) — Includes perculation testing, design certification, stripping septic site, piping,
<br />sand, rock, gravel, cover topsoil, seeding, holding tank, pump, disconnect, control box, alarm, shut-off, testing
<br />and certification.pComplete septic system design will be issued by addendum.
<br />03300 CONCRETE (S) — Includes concrete footings, reinforcing, floor slabs, stoop slab, exterior slabs and
<br />sidewalks concrete sealer on exposed slabs. Provide alternate price for poured foundations, fireplace
<br />foundation, stoop foundation, reinforcing, foundation insulation and heat and cover for foundation construction.
<br />03400 POLISHED CONCRETE (S) — Includes polishing and sealing concrete floors as shown on finish
<br />schedule. Temporary power connection if required.
<br />04200 MASONRY (S) — Includes stone veneer, mortar, precast sills, lintels and column caps, fireplace hearth
<br />stone, water resistive barrier behind stone, flashing and weeps. Provide alternate price for masonry
<br />foundations, fireplace foundation, stoops, reinforcing, core fill, bond beams, foundation insulation and heat and
<br />cover for foundation construction.
<br />05500 STEEL FABRICATION (M) — Includes columns, anchor bolts, beams, lintels.
<br />06000 ROUGH AND FINISH LUMBER (M) — Includes framing lumber, LVL's, trusses, stairs, sheathing,
<br />blocking, Simpson style connectors, baseplate anchor bolts, water and air resistive barriers, interior paneling
<br />and trim, baseboard trim, 15# tar paper for roof, delivered to the jobsite, tax included.
<br />06100 CARPENTRY (S) — Installation only of 05500 Steel Fabrication, 06000 Rough and Finish Lumber,
<br />06400 Architectural Woodwork, 08100 HM Doors and Hardware, 08500 Wood Windows (and window sill
<br />flashing), 10000 Toilet Partitions and Accessories.