Laserfiche WebLink
CHANGE ORDER <br />No. One <br />Date of Issuance: 6/02/2014 Effective Date: <br />Project: Armstrong Boulevard <br />Trail <br />Contract: <br />Owner: City of Ramsey Owner's Contract No.: <br />Date of Contract: November 12, 2013 <br />Contractor: North Metro Asphalt and Contracting Engineer's Project No.: R16.106878 <br />The Contract Documents are modified as follows upon execution of this Change Order: <br />Pay Item No. 26 shall be added to the Schedule of Unit Prices. This item shall be titled "Common Borrow ". <br />Measurement shall be by the Cubic Yard — Loose Volume CY (LV). <br />Payment shall be at the unit price of $12.00 per CY (LV) with an approximate quantity of 1,620 CY(LV) <br />This item shall be added to section 02330 and reference MnDOT 2105.523 specifications. <br />The material used shall be salvaged from the City stockpile. <br />Compensation shall include all cost to load, haul and place the material in accordance with the specifications. <br />There is no change in the Contract Time as a result of this Change Order. <br />CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: <br />Original Contract Price: Original Contract Times: ❑ Working ❑ Calendar days <br />Substantial completion (days or date): <br />$186,141.02 Ready for final payment (days or date): <br />[Increase] [Decrease] from previously approved <br />Change Orders No. to No. <br />[Increase] [Decrease] from previously approved Change Orders <br />No. to No. <br />Substantial completion (days): <br />Ready for final payment (days): <br />Contract Price prior to this Change Order: Contract Times prior to this Change Order: <br />Substantial completion (days or date): <br />$186,141.02 Ready for final payment (days or date): <br />[Increase] [Decrease] of this Change Order: [Increase] [Decrease] of this Change Order: <br />Substantial completion (days or date): <br />S 19,440.00 Ready for final payment (days or date): <br />Contract Price incorporating this Change Contract Times with all approved Change Orders: <br />Substantial completion (days or date): <br />S205,581.02 Ready for final payment (days or date): <br />RECONDED:. ACCEPTED: ACCEPTED: <br />By: By: By: <br />Engineer (Au orized Signature Contractor (Authorized Signature) Owner (Authorized Signature) <br />Date: 6/02/2014 <br />Date: <br />Approved by Funding Agency (if applicable): <br />Date: <br />Date: <br />