Laserfiche WebLink
IMPLEMENTATION PRIORITIES <br />Mid -Term Priority <br />Two projects were identified in the mid-term priority and would remove the final two traffic signals at Ram- <br />sey Blvd (CSAH 561 and Sunfish Lake Blvd (CSAH 571. Both locations need additional project scoping and re- <br />view before a final footprint can be identified; however, less costly and incremental alternatives to previous <br />single -point interchanges as part of the freeway vision were identified. These projects are likely to be 10+ <br />years in the future and as a result will likely require additional project scoping to confirm needs at that time. <br />Removal or partial removal of these remaining signals can be expected to cost 23-45 million dollars. Coupled <br />with immediate and short-term priorities, the mid-term priority projects would accomplish nearly 90 percent of <br />the safety and operational benefits for 1/3 or less of the cost of the freeway. <br />HIGHWAY 10 ACCESS PLANNING STUDY 91 <br />