VII. Project Cost Estimates <br />Site Option B: <br />A. Construction Estimate: <br />1. 6,000 SF Office Building at $250 / SF = $1,500,000 <br />2. 10,200 SF Shop Space at $180 / SF = $1,836,000 <br />3. 6,800 SF Fleet Maintenance at $200 / SF = $1,360,000 <br />4. 45,700 SF Fleet Storage at $125 / SF = $5,712,500 <br />5. 18,100 SF Cold Storage Building at $60 / SF = $1,086,000 <br />6. New Fueling Island with above ground tanks = $200,000 <br />7. Move Salt Storage = $50,000 <br />8. Demolition, Fence and Site Development = $300,000 <br />9. Design & Construction contingency at 5% = $602,000 <br />Construction Estimate = $12,646,500 <br />B. Soft Cost Estimate (Typically Include): <br />1. A/E Fees <br />2. Legal Counsel Review <br />3. Reimbursable Expenses <br />4. Geotechnical Report <br />5. Data /Telecom Wiring <br />6. A/V Systems for Training Room <br />7. Survey <br />8. CM / Project Management Fees <br />9. FF&E (Furniture, Fixtures and equipment) <br />10. SAC (sewer connection fees through Met Council) <br />11. WAC (water connection fees) <br />12. Bond costs <br />13. Plan review fee <br />14. Bid Advertising <br />15. Special Testing (construction) <br />16. Bid document printing <br />17. Builders Risk Insurance <br />18. General Project Contingency <br />Soft Cost Estimate = $1,400,000 <br />Estimated Total Project Cost for 2016 = $14,046,500 <br />This estimate is based on 2016 construction values. <br />Based on construction occurring in 2017 cost should be adjusted by 5% to allow for anticipated inflation. <br />Inflated Construction Estimate for 2017 = $12,646,500 x 5% = $13,278,825 <br />Soft Cost Estimate = $1,500,000 <br />Estimated 2017 Total Project Cost $14,778,825 <br />VII.3 Ramsey Public Works Study <br />DRAFT <br />BKV <br />GROUP <br />