Laserfiche WebLink
Fire Station #2 Costs <br />Soft Costs: <br />Legal $ 840.00 <br />Northern Tech $ 3,750.00 <br />Public Notices $ 714.88 <br />LRRWMO $ 800.00 <br />CES $ 2,281.75 <br />BKV $ 140,252.99 <br />WENCKO $ 1,800.00 <br />Costs thru 4-28-15 $ 150,439.62 <br />BKV remaining on $187,000 Contract $ 51,000.00 <br />FF&E $ 160,000.00 <br />SAC & WAC $ 24,850.00 <br />Plan Review $ 11,595.00 <br />Testing (Construction) $ 7,000.00 <br />Bid Document Printing $ 6,000.00 <br />Builder's risk insurance $ 1,000.00 <br />Contingency $ 50,000.00 <br />Total Soft Costs $ 311,445.00 <br />Hard Costs: <br />Wiring $ 50,000.00 <br />Generator $ 65,000.00 <br />Constructin Contingency $ 160,000.00 <br />Construction Contract Approved $ 3,135,000.00 <br />Total Hard Costs $ 3,410,000.00 <br />Total Costs of Fire Station #2 $ 3,871,884.62 <br />Original Bonding Request (Net of underwriting) $ 3,875,000.00 <br />Bond Overage $ 3,115.38 <br />