My WebLink
|
Help
|
About
|
Sign Out
Home
Agenda - Public Works Committee - 06/15/2004
Ramsey
>
Public
>
Agendas
>
Public Works Committee
>
2000 - 2009
>
2004
>
Agenda - Public Works Committee - 06/15/2004
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
3/13/2025 2:20:32 PM
Creation date
6/16/2004 9:08:13 AM
Metadata
Fields
Template:
Meetings
Meeting Document Type
Agenda
Meeting Type
Public Works Committee
Document Date
06/15/2004
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
56
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
PW CASE <br /> <br />CONSIDER CHANGE ORDER TO GLEN REHBEIN COMPANIES FOR <br />SUNWOOD DRIVE NW AND RHINESTONE STREET NW IMPROVEMENT <br />PROJECT 03-29 <br /> By: Leonard Linton, Civil Engineer <br /> <br />Background: <br /> <br />This project was authorized for construction of MSA Streets in Ramsey Town Center. <br />The work includes extension of trunk sanitary through the Ramsey Town Center Project. <br />The sanitary sewer pipe to be installed is 30". The pipe was connected to the existing <br />system on the west side of Ramsey Boulevard at 143rd Avenue. The existing line is 27". <br />This was known and it was planned that the line would need to be changed to 30" pipe in <br />the fitture, inspection of the line under Ramsey Boulevard indicated that the pipe had a <br />6" sag between manholes. <br /> <br />Ramsey Boulevard will be reconstructed in 2005. The contractor had to dewater to <br />install the new pipe for Ramsey Town Center that connects to the existing manhole. Ttxe <br />contractor has the equipment and pipe onsite at this time. It seems logical to replace the <br />pipe under Ramsey Boulevard now while the contractor is onsite and before the street is <br />reconstructed rather than come back and dewater in 2005 for a short length of pipe. <br />There is additional 27" pipe on the east side of Ramsey Boulevard that will need to be <br />replaced in the future. Replacing this' section of pipe now will eliminate the need to dig <br />into the newly reconstructed street. <br /> <br />Recommendation: <br /> <br />Staff recommends approval of Change Order # 1 to Project 03-29. <br /> <br />Action: <br /> <br />Motion to recommend to City Council approval of Change Order #1 to Improvement <br />Project #03-29 in the amount of $16,847.20. <br /> <br />Reviewed By: <br />Public Works Director <br />Assistant Public Works Director <br /> <br />PW: 06/15/04 <br /> <br /> <br />
The URL can be used to link to this page
Your browser does not support the video tag.