|
C. become familiar with and satisfy Bidder as to all federal, state, and local Laws and Regulations that may affect
<br /> cost,progress,and performance of the Work;
<br /> D. carefully study all: (1)reports of explorations and tests of subsurface conditions at or contiguous to the Site and all
<br /> drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the
<br /> Site(except Underground Facilities) which have been identified in the Supplementary Conditions as provided in
<br /> Paragraph 4.02 of the General Conditions,and(2)reports and drawings of Hazardous Environmental Conditions at
<br /> the Site which have been identified in the Supplementary Conditions as provided in Paragraph 4.06 of the General
<br /> Conditions;
<br /> E. obtain and carefully study(or accept consequences of not doing so)all additional or supplementary examinations,
<br /> investigations, explorations,tests, studies, and data concerning conditions(surface, subsurface, and Underground
<br /> Facilities)at or contiguous to the Site which may affect cost,progress,or performance of the Work or which relate
<br /> to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by
<br /> Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction
<br /> expressly required by the Bidding Documents,and safety precautions and programs incident thereto;
<br /> F. agree at the time of submitting its Bid that no further examinations, investigations, explorations,tests, studies, or
<br /> data are necessary for the determination of its Bid for performance of the Work at the price(s)bid and within the
<br /> times and in accordance with the other terms and conditions of the Bidding Documents;
<br /> G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the
<br /> Work as indicated in the Bidding Documents;
<br /> H. correlate the information known to Bidder, information and observations obtained from visits to the Site, reports
<br /> and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations,
<br /> tests,studies,and data with the Bidding Documents;
<br /> I. promptly give Engineer written notice of all conflicts,errors,ambiguities,or discrepancies that Bidder discovers in
<br /> the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder;and
<br /> J. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms
<br /> and conditions for the performance of the Work.
<br /> 4.08 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with
<br /> every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the
<br /> Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and
<br /> procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that
<br /> Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has
<br /> discovered in the Bidding Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and
<br /> that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and
<br /> conditions for performing and furnishing the Work.
<br /> ARTICLE 5—PRE-BID CONFERENCE
<br /> 5.01 A pre-Bid conference will not be held for this project.
<br /> ARTICLE 6—SITE AND OTHER AREAS
<br /> 6.01 The Site is identified in the Bidding Documents. Easements for permanent structures or permanent changes in
<br /> existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding Documents.All
<br /> additional lands and access thereto required for temporary construction facilities,construction equipment,or storage
<br /> of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor.
<br /> Instructions to Bidders
<br /> 002100-3
<br />
|