1. Reference to standards, specifications,
<br />manuals, or codes of any technical
<br />society, organization, or association, or to
<br />Laws or Regulations, whether such
<br />reference be specific or by implication,
<br />shall mean the standard, specification,
<br />manual, code, or Laws or Regulations in
<br />effect at the time of opening of Bids (or
<br />on the Effective Date of the Agreement if
<br />there were no Bids), except as may be
<br />otherwise specifically stated in the
<br />Contract Documents.
<br />2. No provision of any such standard,
<br />specification, manual or code, or any
<br />instruction of a Supplier shall be effective
<br />to change the duties or responsibilities of
<br />Owner, Contractor, or Engineer, or any
<br />of their subcontractors, consultants,
<br />agents, or employees from those set forth
<br />in the Contract Documents. No such
<br />provision or instruction shall be effective
<br />to assign to Owner, or Engineer, or any
<br />of, their Related Entities, any duty or
<br />authority to supervise or direct the
<br />performance of the Work or any duty or
<br />authority to undertake responsibility
<br />inconsistent with the provisions of the
<br />Contract Documents.
<br />3.03 Reporting and Resolving Discrepancies
<br />A. Reporting Discrepancies
<br />1. Contractor's Review of Contract
<br />Documents Before Starting Work:
<br />Before undertaking each part of the
<br />Work, Contractor shall carefully study
<br />and compare the Contract Documents
<br />and check and verify pertinent figures
<br />therein and all applicable field
<br />measurements. Contractor shall promptly
<br />report in writing to Engineer any conflict,
<br />error, ambiguity, or discrepancy which
<br />Contractor may discover and shall obtain
<br />a written interpretation or clarification
<br />from Engineer before proceeding with
<br />any Work affected thereby.
<br />2. Contractor's Review of Contract
<br />Documents During Performance of
<br />Work: If, during the performance of the
<br />Work, Contractor discovers any conflict,
<br />error, ambiguity, or discrepancy within
<br />the Contract Documents or between the
<br />Contract Documents and any provision of
<br />any Law or Regulation applicable to the
<br />performance of the Work or of any
<br />standard, specification, manual or code,
<br />or of any instruction of any Supplier,
<br />Contractor shall promptly report it to
<br />Engineer in writing. Contractor shall not
<br />proceed with the Work affected thereby
<br />(except in an emergency as required by
<br />Paragraph 6.16.A) until an amendment or
<br />supplement to the Contract Documents
<br />has been issued by one of the methods
<br />indicated in Paragraph 3.04.
<br />3. Contractor shall not be liable to Owner or
<br />Engineer for failure to report any
<br />conflict, error, ambiguity, or discrepancy
<br />in the Contract Documents unless
<br />Contractor knew or reasonably should
<br />have known thereof.
<br />B. Resolving Discrepancies
<br />1. Except as may be otherwise specifically
<br />stated in the Contract Documents, the
<br />provisions of the Contract Documents
<br />shall take precedence in resolving any
<br />conflict, error, ambiguity, or discrepancy
<br />between the provisions of the Contract
<br />Documents and:
<br />a. the provisions of any standard,
<br />specification, manual, code, or
<br />instruction (whether or not
<br />specifically incorporated by
<br />reference in the Contract
<br />Documents); or
<br />b. the provisions of any Laws or
<br />Regulations applicable to the
<br />performance of the Work (unless
<br />such an interpretation of the
<br />provisions of the Contract
<br />Documents would result in violation
<br />of such Law or Regulation).
<br />3.04 Amending and Supplementing Contract
<br />Documents
<br />A. The Contract Documents may be amended to
<br />provide for additions, deletions, and revisions
<br />in the Work or to modify the terms and
<br />conditions thereof by either a Change Order
<br />or a Work Change Directive.