the Contract Documents. Contractor shall at
<br />all times maintain good discipline and order at
<br />the Site.
<br />B. Except as otherwise required for the safety or
<br />protection of persons or the Work or property
<br />at the Site or adjacent thereto, and except as
<br />otherwise stated in the Contract Documents,
<br />all Work at the Site shall be performed during
<br />regular working hours. Contractor will not
<br />permit the performance of Work on a
<br />Saturday, Sunday, or any legal holiday
<br />without Owner's written consent (which will
<br />not be unreasonably withheld) given after
<br />prior written notice to Engineer.
<br />6.03 Services, Materials, and Equipment
<br />A. Unless otherwise specified in the Contract
<br />Documents, Contractor shall provide and
<br />assume full responsibility for all services,
<br />materials, equipment, labor, transportation,
<br />construction equipment and machinery, tools,
<br />appliances, fuel, power, light, heat, telephone,
<br />water, sanitary facilities, temporary facilities,
<br />and all other facilities and incidentals
<br />necessary for the performance, testing,
<br />start-up, and completion of the Work.
<br />B. All materials and equipment incorporated into
<br />the Work shall be as specified or, if not
<br />specified, shall be of good quality and new,
<br />except as otherwise provided in the Contract
<br />Documents. All special warranties and
<br />guarantees required by the Specifications shall
<br />expressly run to the benefit of Owner. If
<br />required by Engineer, Contractor shall furnish
<br />satisfactory evidence (including reports of
<br />required tests) as to the source, kind, and
<br />quality of materials and equipment.
<br />C. All materials and equipment shall be stored,
<br />applied, installed, connected, erected,
<br />protected, used, cleaned, and conditioned in
<br />accordance with instructions of the applicable
<br />Supplier, except as otherwise may be
<br />provided in the Contract Documents.
<br />6.04 Progress Schedule
<br />A. Contractor shall adhere to the Progress
<br />Schedule established in accordance with
<br />Paragraph 2.07 as it may be adjusted from
<br />time to time as provided below.
<br />1. Contractor shall submit to Engineer for
<br />acceptance (to the extent indicated in
<br />Paragraph 2.07) proposed adjustments in
<br />the Progress Schedule that will not result
<br />in changing the Contract Times. Such
<br />adjustments will comply with any
<br />provisions of the General Requirements
<br />applicable thereto.
<br />2. Proposed adjustments in the Progress
<br />Schedule that will change the Contract
<br />Times shall be submitted in accordance
<br />with the requirements of Article 12.
<br />Adjustments in Contract Times may only
<br />be made by a Change Order.
<br />6.05 Substitutes and "Or -Equals"
<br />A. Whenever an item of material or equipment is
<br />specified or described in the Contract
<br />Documents by using the name of a proprietary
<br />item or the name of a particular Supplier, the
<br />specification or description is intended to
<br />establish the type, function, appearance, and
<br />quality required. Unless the specification or
<br />description contains or is followed by words
<br />reading that no like, equivalent, or "or -equal"
<br />item or no substitution is permitted, other
<br />items of material or equipment or material or
<br />equipment of other Suppliers may be
<br />submitted to Engineer for review under the
<br />circumstances described below.
<br />1. "Or -Equal" Items: If in Engineer's sole
<br />discretion an item of material or
<br />equipment proposed by Contractor is
<br />functionally equal to that named and
<br />sufficiently similar so that no change in
<br />related Work will be required, it may be
<br />considered by Engineer as an "or -equal"
<br />item, in which case review and approval
<br />of the proposed item may, in Engineer's
<br />sole discretion, be accomplished without
<br />compliance with some or all of the
<br />requirements for approval of proposed
<br />substitute items. For the purposes of this
<br />Paragraph 6.05.A.1, a proposed item of
<br />material or equipment will be considered
<br />functionally equal to an item so named if:
<br />a. in the exercise of reasonable
<br />judgment Engineer determines that:
<br />1) it is at least equal in materials of
<br />construction, quality, durability,
<br />Standard General Conditions
<br />00 72 00-18
<br />
|