37. Site —Lands or areas indicated in the Contract Documents as being furnished by Owner
<br />upon which the Work is to be performed, including rights -of -way and easements, and
<br />such other lands furnished by Owner which are designated for the use of Contractor.
<br />38. Specifications —The part of the Contract that consists of written requirements for
<br />materials, equipment, systems, standards, and workmanship as applied to the Work,
<br />and certain administrative requirements and procedural matters applicable to the
<br />Work.
<br />39. Subcontractor —An individual or entity having a direct contract with Contractor or with
<br />any other Subcontractor for the performance of a part of the Work.
<br />40. Substantial Completion —The time at which the Work (or a specified part thereof) has
<br />progressed to the point where, in the opinion of Engineer, the Work (or a specified
<br />part thereof) is sufficiently complete, in accordance with the Contract Documents, so
<br />that the Work (or a specified part thereof) can be utilized for the purposes for which it
<br />is intended. The terms "substantially complete" and "substantially completed" as
<br />applied to all or part of the Work refer to Substantial Completion thereof.
<br />41. Successful Bidder —The Bidder whose Bid the Owner accepts, and to which the Owner
<br />makes an award of contract, subject to stated conditions.
<br />42. Supplementary Conditions —The part of the Contract that amends or supplements
<br />these General Conditions.
<br />43. Supplier —A manufacturer, fabricator, supplier, distributor, materialman, or vendor
<br />having a direct contract with Contractor or with any Subcontractor to furnish materials
<br />or equipment to be incorporated in the Work by Contractor or a Subcontractor.
<br />44. Technical Data —Those items expressly identified as Technical Data in the
<br />Supplementary Conditions, with respect to either (a) subsurface conditions at the Site,
<br />or physical conditions relating to existing surface or subsurface structures at the Site
<br />(except Underground Facilities) or (b) Hazardous Environmental Conditions at the Site.
<br />If no such express identifications of Technical Data have been made with respect to
<br />conditions at the Site, then the data contained in boring logs, recorded measurements
<br />of subsurface water levels, laboratory test results, and other factual, objective
<br />information regarding conditions at the Site that are set forth in any geotechnical or
<br />environmental report prepared for the Project and made available to Contractor are
<br />hereby defined as Technical Data with respect to conditions at the Site under
<br />Paragraphs 5.03, 5.04, and 5.06.
<br />45. Underground Facilities —All underground pipelines, conduits, ducts, cables, wires,
<br />manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any
<br />encasements containing such facilities, including but not limited to those that convey
<br />electricity, gases, steam, liquid petroleum products, telephone or other
<br />communications, fiber optic transmissions, cable television, water, wastewater, storm
<br />water, other liquids or chemicals, or traffic or other control systems.
<br />46. Unit Price Work —Work to be paid for on the basis of unit prices.
<br />47. Work —The entire construction or the various separately identifiable parts thereof
<br />required to be provided under the Contract Documents. Work includes and is the
<br />result of performing or providing all labor, services, and documentation necessary to
<br />produce such construction; furnishing, installing, and incorporating all materials and
<br />equipment into such construction; and may include related services such as testing,
<br />start-up, and commissioning, all as required by the Contract Documents.
<br />EJCDC® C-700, Standard General Conditions of the Construction Contract.
<br />Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies,
<br />and American Society of Civil Engineers. All rights reserved. Page 4 of 65