stormwater improvements. This component is still not completed. The Developer has noted that unexpected grading <br />activities (export/import/soil corrections/suitable soil supply) has led to certain delays in completing mass grading <br />for the development. While Staff has been flexible in permitting new dwellings to be constructed, Staff <br />recommends that no further extensions on this aspect be allowed, and that this should be completed before <br />additional permits are issued. Staff believes this aspect of the project should be completed before additional <br />activities are commenced to avoid furthering the level of uncompleted aspects of the project. <br />Funding Source: <br />All costs associated with reviewing the request are the responsibility of the Applicant. <br />Recommendation: <br />Staff recommends approval of the Amendment to the Development Agreement for COR North Commons as <br />attached. <br />Action: <br />Motion to adopt Resolution #17-09-230 approving the Amendment to Development Agreement for COR Three <br />North Commons. <br />Attachments <br />Site Location Map <br />Amendment to Development Agreement <br />Developer Written Request <br />Phasing Proposal <br />ORIGINAL Development Agreement <br />Resolution #17-09-230 <br />Form Review <br />Inbox Reviewed By Date <br />Kurt Ulrich Kurt Ulrich 09/07/2017 10:59 AM <br />Form Started By: Tim Gladhill Started On: 08/30/2017 07:54 AM <br />Final Approval Date: 09/07/2017 <br />