EXHIBIT B <br />Improvement Project <br />Updated November 8, 2018. Final Costs Displayed. <br />Improvement Type <br />Phase 1A _ Phase 1B <br />Roadway $460,744 $ 627,790 <br />Roadway Transitions $ 40,045 $ 12,554 <br />Right Turn Lanes $ - $ 4,899 <br />Trails/Sidewalks $ 10,421 $ 38,350 <br />Storm Water Management $ - $ 48,000 <br />Street Lighting $ 38,952 $ 41,048 <br />Trunk Water <br />Trunk Sanitary Sewer <br />Total Costs/Phase <br />$148,972 $ 241,258 <br />$ 94,358 $ 551,025 <br />$793,492 $1,564,924 <br />Total Costs Less Public Utilities $550,162 $ 772,641 <br />NOTE: Riverstone requested certain Phase 1B improvements to be constructed early. As a result, Phase 1B costs <br />were increased by $60,456, to account for a temporary gravel road. Riverstone will be assessed 100% of this <br />additional cost. This is not reflected in Exhibit B; this is reflected in Exhibit C. <br />