PAY ESTIMATE NO
<br />BASE BID
<br />ALTERNATIVE A
<br />BASE BID PLUS ALTERNATIVES
<br />BASE AREA
<br />IP 19-01 Ford Brook Estates Street Reconstructions
<br />Pay Estamite
<br />4
<br />$ 249,901.55
<br />$ 12,601.70
<br />$ 262,503.25
<br />$ 4,448.00
<br />$ 4,448.00
<br />$ 255,188.15
<br />$ 12,601.70
<br />$ 267,789.85
<br />Item No,
<br />MnDot No.
<br />Item Description
<br />Unit
<br />CONTRACT AMOUNT
<br />PAY THIS PERIOD
<br />PAID TO DATE
<br />Estimated
<br />Quantity
<br />Unit Price
<br />Extension
<br />Quantity
<br />Extension
<br />Quantity
<br />Extension
<br />1
<br />2021.501
<br />Mobilization
<br />LS 1
<br />$25,000.00
<br />$ 25,000.00
<br />0.0
<br />$ -
<br />1.0
<br />$ 25,000.00
<br />2
<br />2101.502
<br />Clearing Tree
<br />TREE 4
<br />$ 450.00
<br />$ 1,800.00
<br />0
<br />$ - 4
<br />$ 1,800.00
<br />3
<br />2101.507
<br />Grubbing Tree
<br />TREE 4
<br />$ 350.00
<br />$ 1,400.00
<br />0
<br />$ - 4
<br />$ 1,400.00
<br />4
<br />2104.501
<br />Remove Pipe Culverts
<br />LF 142
<br />$ 15.00
<br />$ 2,130.00
<br />0
<br />$ - 142
<br />$ 2,130.00
<br />5
<br />2104.503 Remove Concrete Pavement - Driveways SF 1,370
<br />$ 1.15 $ 1,575.50
<br />0 $ - 1,574
<br />$ 1,810.10
<br />6
<br />7
<br />2104.505 Remove Bituminous Pavement - Driveways
<br />2104.505
<br />Remove Bituminous Pavement - Roadway
<br />SY
<br />SY
<br />87
<br />2,641
<br />$ 5.00 $
<br />435.00
<br />$ 2.25 $ 5,942.25
<br />0
<br />0
<br />88
<br />2,641
<br />440.00
<br />$ 5,942.25
<br />8
<br />2104.505
<br />Remove Gravel Pavement - Driveways
<br />SY
<br />117
<br />$ 4.50 $ 526.50
<br />0
<br />117 $
<br />526.50
<br />9
<br />10
<br />11
<br />12
<br />2104.507
<br />2104,511
<br />2104.513
<br />2104.521
<br />Subgrade Excavation, Remove Unsuitable Material (EV)
<br />Sawing Concrete Pavement - Full Depth
<br />Sawing Bituminous Pavement - Full Depth
<br />Salvage and Install Retaining Wall
<br />CY
<br />LF
<br />LF
<br />LF
<br />2,097
<br />110
<br />113
<br />52
<br />$ 11.50 $ 24,115.50
<br />$ 5.00 $ 550.00
<br />$ 3.00 $ 339.00
<br />$ 100.00 $ 5,200.00
<br />0
<br />0
<br />0
<br />26
<br />$
<br />$
<br />$ 2,600.00
<br />2,220 $ 25,530.00
<br />112 $ 560.00
<br />84 $ 252.00
<br />52 $ 5,200.00
<br />13
<br />14
<br />15
<br />16
<br />2104.523
<br />2104.523
<br />2105.501
<br />2105.522
<br />Salvage and Install Mail Box Support
<br />Temporary Mail Box Cluster
<br />Common Excavation (EV)
<br />EA
<br />EA
<br />CY
<br />Select Granular Borrow (CV) CY
<br />8
<br />1
<br />175
<br />2,430
<br />$ 125.00 $ 1,000.00
<br />$ 375.00 $ 375.00
<br />$ 20.00 $ 3,500.00
<br />$ 13.50 $ 32,805,00
<br />0
<br />0
<br />0
<br />0
<br />$
<br />8 $ 1,000.00
<br />1 $ 375.00
<br />85 $ 1,700.00
<br />2,324 $ 31,374.00
<br />17
<br />18
<br />19
<br />20
<br />2105.604
<br />2112.501
<br />2118.502
<br />2130.501
<br />Geotextile Fabric Type V SY
<br />Subgrade Preparation RDST
<br />Aggregate Surfacing, Class 5 Modified (LV) - Driveways CY
<br />Water
<br />MGAL
<br />3,036
<br />8
<br />16
<br />16
<br />$ 1.85 $ 5,616.60
<br />$ 300.00 $ 2,400.00
<br />$ 65.00 $ 1,040.00
<br />$ 45.00 $ 720.00
<br />0
<br />0
<br />0
<br />0.0
<br />$
<br />3,036 $ 5,616.60
<br />8 $ 2,400.00
<br />24 $ 1,560.00
<br />17.5 $ 787.50
<br />21
<br />2211.503
<br />Aggregate Base Class 5 Modified (CV) CY
<br />380
<br />$ 40.00 $ 15,200.00
<br />0
<br />372 $ 14,880.00
<br />22
<br />2232.501
<br />Mill Bituminous Pavement (1.5") SY
<br />126
<br />$ 10.00 $ 1,260.00
<br />0
<br />126 $ 1,260.00
<br />23
<br />2357.502
<br />Bituminous Material for Tack Coat GAL
<br />200
<br />$ 3.00 $ 600.00
<br />0
<br />225 $ 675.00
<br />24
<br />2360.501
<br />Type SP 9.5 Wearing Course Mixture (SPWEA340C) (1.5") TON
<br />230
<br />$ 95.50 $ 21,965.00
<br />0
<br />$
<br />237 $ • 22,633.50
<br />25
<br />2360.501
<br />Type SP 9.5 Wearing Course Mixture (SPWEA34C) Driveways
<br />(2.0")
<br />TON
<br />10
<br />$ 150.00 $ 1,500.00
<br />0
<br />10 $ 1,500.00
<br />26
<br />2360.502
<br />Type SP 12.5 Non Wearing Course Mixture (SPNWB330C) (2.0") TON
<br />302
<br />$ 81.75 $ 24,688.50
<br />0
<br />354 $ 28,939.50
<br />27
<br />2501.511
<br />15" CS Pipe Culvert
<br />LF
<br />127
<br />$ 56.00 $ 7,112.00
<br />0
<br />$
<br />148 $ 8,288.00
<br />28
<br />2501.515
<br />15" CS Pipe Apron
<br />EA
<br />8
<br />$ 630.00 $ 5,040.00
<br />0
<br />8 $ 5,040.00
<br />29
<br />2501.602
<br />Clean Pipe Culvert
<br />EA
<br />5
<br />$ 400.00 $ 2,000.00
<br />0
<br />5 $ 2,000.00
<br />30
<br />2502.541
<br />4" Perf. Pipe Drain
<br />LF
<br />721
<br />$ 15.00 $ 10,815.00
<br />0
<br />$
<br />721 $ 10, 815.00
<br />31
<br />2506.501
<br />Construct Drainage Structure Design 48-4020
<br />LF
<br />5.3
<br />$ 455.00 $ 2,411.50
<br />0.0
<br />$
<br />5.3 $ 2,411.50
<br />32
<br />2506.516
<br />Furnish & Install Casting Assembly - Storm
<br />EA
<br />1
<br />$ 850.00 $ 850.00
<br />0
<br />1 $ 850.00
<br />33
<br />2506.522
<br />Adjust Frame & Ring Casting
<br />EA
<br />1
<br />$ 650.00 $ 650.00
<br />0
<br />$
<br />1 $ 650.00
<br />34
<br />2531.507
<br />6" Concrete Driveway Pavement
<br />SF
<br />1,377
<br />$ 13.25 $ 18,245.25
<br />0
<br />1,499 $ 19, 861.75
<br />35
<br />36
<br />37
<br />38
<br />39
<br />40
<br />41
<br />42
<br />43
<br />44
<br />45
<br />46
<br />2540.601
<br />2563.601
<br />2572.501
<br />2573.502
<br />2573.530
<br />2573.530
<br />2574.508
<br />2574.525
<br />2575.501
<br />2575.502
<br />2575.505
<br />2575.562
<br />Landscape Restoration
<br />Traffic Control
<br />Tree Protection Fence
<br />Silt Fence, Type MS
<br />Stone Drain Inlet Protection - Manhole
<br />Storm Drain Inlet Protection - Culvert
<br />Fertilizer Type 3
<br />Topsoil (LV)
<br />Hydroseeding
<br />Seed Mixture 25-151
<br />Sodding Type Lawn
<br />Hydraulic Matrix Type Mulch
<br />LS
<br />LS
<br />LF
<br />LF
<br />EA
<br />EA
<br />LBS
<br />CY
<br />ACRE
<br />LBS
<br />SY
<br />LBS
<br />1
<br />1
<br />155
<br />220
<br />1
<br />20
<br />52
<br />173
<br />0.52
<br />63
<br />83
<br />1,040
<br />$ 4,500.00 $ 4,500.00
<br />$ 1,500.00 $ 1,500.00
<br />$ 2.75 $ 426.25
<br />$ 2.75 $ 605.00
<br />$ 225.00
<br />$ 120.00
<br />$ 1.10
<br />$ 40.00
<br />$ 4,500.00
<br />$ 3.50
<br />$ 16.00
<br />$ 0.55
<br />$ 225.00
<br />$ 2,400.00
<br />$ 57.20
<br />$ 6,920.00
<br />$ 2,340.00
<br />$ 220.50
<br />$ 1,328.00
<br />$ 572.00
<br />0.0
<br />0
<br />0
<br />0
<br />0
<br />0
<br />0
<br />13
<br />0.00
<br />0
<br />83
<br />0
<br />$
<br />$
<br />$
<br />$
<br />$ 520.00
<br />$
<br />$ 1,328.00
<br />$
<br />1.0 $ 4,500.00
<br />1 $ 1,500.00
<br />85 $ 233.75
<br />220 $ 605.00
<br />1 $ 225.00
<br />12 $ 1,440.00
<br />52 $ 57.20
<br />173 $ 6,920.00
<br />0.52 $ 2,340.00
<br />74 $ 259.00
<br />83 $ 1,328.00
<br />1,040 $ 572.00
<br />TOTAL BID
<br />$ 249,901.55
<br />$ 4,448.00
<br />$ 255,188.15
<br />ALTERNATE A
<br />Item No.
<br />MnDot Na.
<br />Item Description
<br />Unit
<br />CONTRACT AMOUNT
<br />PAY THIS PERIOD
<br />PAID TO DATE
<br />Estimated
<br />Quantity
<br />Unit Price
<br />Extension
<br />Quantity
<br />Extension
<br />Quantity
<br />Extension
<br />1
<br />2101.502
<br />Clearing Tree
<br />TREE
<br />1
<br />$ 450.00
<br />$ 450.00
<br />0
<br />$ -
<br />1
<br />$ 450.00
<br />2
<br />2101.507
<br />Grubbing Tree
<br />TREE
<br />1
<br />$ 350.00
<br />$ 350.00
<br />0
<br />$ -
<br />1
<br />$ 350.00
<br />3
<br />2104.503
<br />Remove Concrete Pavement - Driveways
<br />SF
<br />208
<br />$ 1.15
<br />$ 239.20
<br />0
<br />$ -
<br />208
<br />$ 239.20
<br />4
<br />2104,507
<br />Subgrade Excavation, Remove Unsuitable Material (EV)
<br />CY
<br />160
<br />$ 11.50
<br />$ 1,840.00
<br />0
<br />$ -
<br />160
<br />$ 1,840.00
<br />5
<br />2105.501
<br />Common Excavation (EV)
<br />CY
<br />10
<br />$ 25.00
<br />$ 250.00
<br />0
<br />$ -
<br />10
<br />$ 250.00
<br />6
<br />2105.522
<br />Select Granular Borrow (CV)
<br />CY
<br />192
<br />$ 13.50
<br />$ 2,592.00
<br />0
<br />$ -
<br />192
<br />$ 2,592.00
<br />7
<br />2105.604
<br />Geotextile Fabric Type V
<br />SY
<br />240
<br />$ 2.00
<br />$ 480.00
<br />0
<br />$ -
<br />240
<br />$ 480.00
<br />8
<br />2211.503
<br />Aggregate Base Class 5 Modified (CV)
<br />CY
<br />32
<br />$ 39.50
<br />$ 1,264.00
<br />0
<br />$ -
<br />32
<br />$ 1,264.00
<br />9
<br />2357.502
<br />Bituminous Material for Tack Coat,
<br />GAL
<br />17
<br />$ 3.00
<br />$ 51.00
<br />0
<br />$ -
<br />17
<br />$ 51.00
<br />10
<br />2360.501
<br />Type SP 9.5 Wearing Course Mixture (SPWEA340C) (1.5")
<br />TON
<br />20
<br />$ 95.50
<br />$ 1,910.00
<br />0
<br />$ -
<br />20
<br />$ 1,910.00
<br />11
<br />2360.502
<br />Type SP 12.5 Non Wearing Course Mixture (SPNWB330C) (2.0")
<br />TON
<br />26
<br />$ 81.75
<br />$ 2,125.50
<br />0
<br />$ -
<br />26
<br />$ 2,125.50
<br />12
<br />2571.502
<br />Decidious Tree 2.5" Cal. BR =
<br />EA
<br />1
<br />$ 1,050.00
<br />$ 1,050.00
<br />0
<br />$ -
<br />1
<br />$ 1,050.00
<br />TOTAL BID
<br />$ 12,601.70
<br />$ -
<br />$ 12,601.70