Councilmember introduced the following resolution and moved for its adoption:
<br /> RESOLUTION#22-022
<br /> RESOLUTION AUTHORIZING FINAL PAYMENT TO NORTH VALLEY,INC.,FOR
<br /> IMPROVEMENT PROJECT#21-02,TIGER STREET RECONSTRUCTION
<br /> WHEREAS, the City of Ramsey proposes to reconstruct Tiger Street between Armstrong
<br /> Boulevard and 173rd Avenue in 2021 as identified in the 2021-2030 Capital Improvement Program; and
<br /> WHEREAS, pursuant to Ramsey City Council resolution#20-259, adopted November 10, 2020,the City
<br /> Council accepted the quotes of Bolton & Menk, Inc. to provide topographic survey services, and Chosen
<br /> Valley Testing for the geotechnical evaluation services required to design and prepare plans and
<br /> specifications for said improvements; and
<br /> WHEREAS, City Staff has received the topographic survey and geotechnical evaluations and has
<br /> the capacity to prepare plans and specifications for improvement project #21-02, Tiger Street
<br /> Reconstruction; and
<br /> WHEREAS,pursuant to Ramsey City Council resolution#21-009, adopted January 12, 2021,the
<br /> City Engineer has prepared plans and specifications for the purpose of advertising for bids for the same
<br /> improvements; and
<br /> WHEREAS, pursuant to Ramsey City Council resolution #21-085, adopted April 13, 2021, the
<br /> City Council approved final plans and specifications as prepared by the City Engineer and authorized
<br /> advertisement for bids for said improvements; and
<br /> WHEREAS,pursuant to Ramsey City Council resolution#21-13 9, adopted May 25, 2021, the bid
<br /> of North Valley, Inc., of Nowthen, Minnesota, in the amount of$224,552.19, for the construction of said
<br /> improvements was accepted; the Mayor and City Administrator were authorized and directed to enter into
<br /> a contract with said bidder for the construction of said improvements for and on behalf of the City of
<br /> Ramsey, and the City Administrator was hereby authorized to execute the proposal from Bolton& Menk,
<br /> Inc. to provide construction staking services for said improvements in a total not-to-exceed amount of
<br /> $4,680 for the project; and
<br /> WHEREAS, pursuant to Ramsey City Council Resolution #21-246 adopted Change Order No.1
<br /> in the amount of$50,638.69 allowing the removal of 1,093 cubic yards of unsuitable materials from the
<br /> road core which were discovered during construction and placement of 1,093 cubic yards of select
<br /> granular material. The quantities of which were significantly greater than the approved plans and
<br /> specifications accounted for; and
<br /> WHEREAS, as of February 22,2022, $241,207.15 has been paid to date; and
<br /> WHEREAS, the Engineer Technician IV has inspected the completed work and recommends
<br /> final payment to North Valley, Inc. of Nowthen, Minnesota for Improvement Project#21-02, Tiger Street
<br /> Reconstruction, in the amount of$12,695.11.