My WebLink
|
Help
|
About
|
Sign Out
Home
Agenda - Public Works Committee - 10/18/2005
Ramsey
>
Public
>
Agendas
>
Public Works Committee
>
2000 - 2009
>
2005
>
Agenda - Public Works Committee - 10/18/2005
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
3/13/2025 2:29:03 PM
Creation date
10/17/2005 9:01:37 AM
Metadata
Fields
Template:
Meetings
Meeting Document Type
Agenda
Meeting Type
Public Works Committee
Document Date
10/18/2005
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
38
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
CASE <br /> <br />PROJECT CLOSEOUT OF TH 47 IMPROVEMENT PROJECT <br /> By: Steven Jankowski, City Engineer <br /> <br />Background: <br /> <br />In May of 2000 construction was initiated on TH 47 between 142nd Avenue and Alpine <br />Drive which created a divided median with turn lanes and substantially widened the <br />driving lanes. The City undertook the role of lead agency for this project as. it was a high <br />priority for the City. MnDOT assisted with this project by providing construction <br />inspection and preparation of pay estimates for work performed by the contractor. <br /> <br />Thc project was opened to traffic in the fall of 2000, however, approximately. S500,000 of <br />thc total $4.9 million project was incurred for work with was performed over the <br />succeeding construction year of 2001. The Work done in 2001 included the installation of <br />landscaping which the specifications stated must survive for two years before final <br />payment can be processed. The last payment which the City processed on this project was <br />made in August of 2002. The prime contractor on this project, Richard Knutson Inc. has <br />never requested any additional payment, however, a landscaping subcontractor which <br />provided trees for the project has request a bonus payment Provided in the specifications <br />for having over a 90% planting survival rate. MnDOT has reviewed this request and <br />determined this bonus payment to be appropriate. <br /> <br />At the present time, there are two pay estimates which need to be processed in order to <br />finalize this project, vouchers 12 and 13. A summary of these two pay estimates are <br />attached. The work associated with this project was separated into three individual <br />pro. jeers each with subcategories for road and storm sewer improvements, plus an' <br />additional designation for City water and sewer improvements. The first five project <br />categories have an 80% federal reimbursement and the Sunwood Drive storm sewer, <br />payment group 6, is being reimbursed 44%.-The total payment to the contractor will be <br />$39,171.07. The City share of this amount will be $15,841.24 with $9,942.18 of this <br />amount attributable to the sewer and water trunk fund. The.remaining $5,899.06 would <br />be taken from the Public Improvement Revolving (PIR) fund. <br /> <br />Recommendation: <br /> <br />Start' recommends payment to Richard Knutson Inc. of partial payment voucher 12 in the <br />amount of $ 33,595.07, and final payment voucher 13 in the amount of $5,576.00 and <br />th~l reimbursement from federal funds be submitted in the amount of $23,329.83. <br /> <br />Action: <br /> <br />Motion to recommend to Richard Knutson Inc. City Council payment of partial payment <br />~,oucher 12 in the amount of $ 33,595.07, and final payment voucher 13 in the amount of <br /> <br />-23- <br /> <br /> <br />
The URL can be used to link to this page
Your browser does not support the video tag.