Mr.Bruce Westby,P.E. <br /> September 26,2022 <br /> Page 2 of 3 <br /> • Clear and grub the area of The COR bounded by Sunwood Drive, Bunker Lake Boulevard, <br /> Armstrong Boulevard and Center Street, <br /> • Strip off topsoil for the above area and stockpile the material, <br /> • Dewater the area to allow for deep excavations to occur, <br /> • Excavate the pond, placing the material in locations identified within The COR, <br /> • Place a 2 ft thick clay liner in the pond from the bottom up to the normal water level, <br /> • Fine grade the area of the regional stormwater retention pond, and <br /> • Revegetate all areas disturbed by construction. <br /> We will provide construction cost estimates associated with the improvements. <br /> SCOPE OF SERVICES <br /> Our anticipated scope of services will be as follows: <br /> • Complete a drone flight of the area to provide a current aerial image of the area.The drone <br /> flight will provide a level of accuracy of 0.1 ft horizontal and 0.3 ft vertical.This will allow for <br /> accurate estimations of excavations and fill volumes required to construct the Waterfront and <br /> move the material to adjacent lots within The COR area. <br /> • Update the stormwater model to analyze elevations within the Waterfront and impacts <br /> associated with filling existing stormwater ponds across The COR. <br /> • Analyze the potential for filling the wetland that was created in the southeast quadrant of <br /> Bunker Lake Boulevard and Armstrong Boulevard.This will be completed under a separate <br /> contract and the results will be discussed in the updated report. <br /> • Analyze previous report assumptions and update proposed horizontal and vertical elevations <br /> associated with the roadways and public utilities within The COR area. Develop current <br /> construction cost estimates based on the analysis. <br /> • Prepare a report detailing the findings of our analyses.This will likely be in the form of an <br /> update to previously prepared reports. <br /> No geotechnical analysis will be performed for the project, although previous soil borings completed for <br /> the area will be reviewed. <br /> SUMMARY OF FEES <br /> We have prepared preliminary fee estimates based on our understanding of the work to be performed. <br /> We estimate fees will be as presented below: <br /> Task Fees <br /> Drone Flight $ 2,880.00 <br /> Stormwater Analysis $ 7,200.00 <br /> Roadway and Public Utility Analysis $ 9,680.00 <br /> Report preparation, Including Figures $ 4,420.00 <br /> Not-To-Exceed Fees $24,180.00 <br /> The fees in the above table represent not-to-exceed costs based on the scope present above. <br /> Bolton&Menk is an equal opportunity employer. l <br /> I <br />