<br />Councilmember Musgrove introduced the following resolution and moved for its adoption:  
<br />  
<br />RESOLUTION #23-078  
<br />  
<br />RESOLUTION ACCEPTING BIDS AND AWARDING CONTRACT FOR  
<br />IMPROVEMENT PROJECT #23-12, HY-10 RAMSEY IMPROVEMENTS  
<br />  
<br />WHEREAS, the City of Ramsey proposes to reconstruct the existing segments of Ferret  
<br />thth 
<br />Street, 146 Avenue and 147 Avenue within the HY-10 Ramsey plat; and  
<br />  
<br />WHEREAS, the City proposes to extend Ferret Street to connect to Bunker Lake  
<br />Boulevard to provide a secondary access route to properties within the HY-10 Ramsey plat; and  
<br />  
<br />WHEREAS, the City proposes to extend sanitary sewer and watermain utilities under  
<br />th 
<br />147 Avenue and Ferret Street to allow all properties within the HY-10 Ramsey plat, which is  
<br />located within the City’s MUSA, to be served by municipal utilities; and  
<br />  
<br />WHEREAS, pursuant to Ramsey City Council Resolution #21-349 adopted December  
<br />14, 2021, the City Council accepted a design services proposal from Bolton & Menk, Inc. to  
<br />update the Feasibility Report, prepare plans and specifications, and solicit bids for Improvement  
<br />Project #23-12; and  
<br />  
<br />WHEREAS, pursuant to Ramsey City Council Resolution #23-054, adopted March 14,  
<br />2023, the City Council approved the additional services to be performed by Bolton and Menk to  
<br />complete plans and specifications, approved the construction services proposal submitted by  
<br />Bolton and Menk, approved plans and specifications as prepared by Bolton and Menk, and  
<br />authorized advertising for bids for said improvements; and  
<br />  
<br /> WHEREAS, bids were advertised in the Anoka Union Herald, Finance and Commerce  
<br />on March 3, and March 10th, 2023; and  
<br />  
<br /> WHEREAS, ten (10) bids were received, opened and tabulated on April 13, 2023 and  
<br />the following bids were found to comply with the approved plans and specifications and  
<br />advertisements for bids; and  
<br />  
<br />  
<br />Company Bid  
<br />  
<br />Douglas-Kerr Underground, L.L.C. $1,398,953.30  
<br />  
<br />Northern Lines Contracting $1,466,719.60  
<br />  
<br />S.R. Weidema $1,497,831.15  
<br />  
<br />Dave Perkins Contracting, Inc. $1,499,999.96  
<br />  
<br />Kuechle Underground Inc. $1,561.790.70  
<br />  
<br />North Pine Aggregate, Inc. $1,615,148.90  
<br />  
<br />  
<br />RL Larson Excavating, Inc.  $1,636,109.27  
<br />  
<br />Park Construction Company $1,709,008.20  
<br />  
<br />Northdale Construction Company, Inc. $1,780,420.56  
<br />  
<br />Meyer Contracting Inc. $2,062,193.79  
<br />  
<br />  
<br />
<br />
								 |