MnDOT Contract No.: 1052605
<br />usable, and aesthetically acceptable condition. The County will be responsible for oversize, overweight,
<br />and special use permits.
<br />B. City Responsibilities. The City will be responsible for maintenance of any sidewalk and/or trail on the
<br />bridges and approach panels, without any cost to the State. Maintenance includes, but is not limited to,
<br />snow, ice, debris, and graffiti removal, pavement marking maintenance, and signing maintenance. The
<br />City will own and maintain non-standard (aesthetic) elements such as decorative lighting, ornamental
<br />metal railing and any elements later added to the bridge. Maintenance of the aesthetic elements
<br />includes, but is not limited to, graffiti removal and other routine maintenance activities necessary to
<br />perpetuate the aesthetic elements in a safe, usable, and aesthetically acceptable condition.
<br />C. State Responsibilities. The State will perform structural inspections and major maintenance of the
<br />bridges without any cost to the County. Major maintenance includes all structural related maintenance,
<br />including expansion joint flushing, deck crack sealing, crack sealing trails on the bridge and on approach
<br />panels, painting, overlays, redecking and rehabilitation of the bridge, concrete bridge approach panels,
<br />and structurally -supported signing on the bridge. The State will be responsible for maintenance of all
<br />guardrails on TH 10 below the bridges, roadway signing that is attached to the bridges for the purpose
<br />of TH 10 traffic, non -ornamental fencing on the Trunk Highway Right -of -Way, and graffiti removal
<br />within the control of access below the bridges. The State will determine the safe load rating for the
<br />bridges. The State will provide emergency response for traffic hits and restitution from insurance
<br />companies or private parties who have damaged the bridges.
<br />9. State Cost and Payment by the State
<br />9.1. State Cost. The State's cost for grading, bituminous surfacing, ADA improvements, retaining walls, noise
<br />walls, high tension cable guardrail, TMS, lighting, and roundabouts construction is defined in the
<br />construction plan and the attached Schedule "I" and is reflective of the Participation Distribution prepared
<br />by the Office of State Aid for Local Transportation.
<br />A. State Federal -Aid Funds and State Match to the Federal -Aid Funds. $3,200,000.00 is the State Federal -
<br />Aid funded portion and $800,000.00 is the State Match to the State Federal -Aid funds of the State
<br />construction cost share and will be paid to the County through the State Aid Finance Office under the
<br />Delegated Contract Process (State Aid Manual, Chapter 5.3). The State Federal -Aid funds and State
<br />match to Federal -Aid funds will be capped at $4,000,000.00.
<br />B. State SRC Funds. $8,000,000.00 is the capped amount of the estimated State funded construction cost
<br />share and will be paid to the County through the State Aid Finance Office under the Delegated Contract
<br />Process (State Aid Manual, Chapter 5.3).
<br />C. State Bond Funds. $10,350,337.45 is the capped amount of the estimated State bond funded
<br />construction cost share and will be paid to the County through the State Aid Finance Office under the
<br />Delegated Contract Process (State Aid Manual, Chapter 5.3).
<br />9.2. Limitations of State Payment; No State Payment to Contractor. The State's participation in the contract
<br />construction is limited to the estimated amounts shown in Article 10.1, and the State's participation will
<br />not change except by a mutually agreed written amendment to this Agreement. The State's payment
<br />obligation extends only to the County. The County's contractor is not intended to be and will not be
<br />deemed to be a third -party beneficiary of this Agreement. The County's contractor will have no right to
<br />receive payment from the State. The State will have no responsibility for claims asserted against the
<br />County by the County's contractor.
<br />9.3. Schedule "YThe Preliminary Schedule "I" includes all anticipated State participation construction items
<br />covered under this Agreement. The Preliminary Schedule "I" is based upon estimated quantities and
<br />estimated unit prices. After the construction contract is awarded, the State will prepare a Revised Schedule