We recommend bedding material be thoroughly compacted around the pipes. We recommend <br />trench backfill above the pipes be compacted to a minimum of 95 percent beneath pavements, the <br />exception being within 3 feet of the proposed pavement subgrade, where 100 percent of standard <br />Proctor density is required. In landscaped areas we recommend a minimum compaction of 90 <br />percent. <br />4.4 Pavement Recommendations <br />The City of Ramsey may have standard plates that dictate bituminous pavement design. If so, we <br />assume the pavements be designed in accordance with the appropriate standard plates. The <br />following paragraphs provide general pavement recommendations in the absence of standard <br />plates. <br />Reconstruction In areas that will be reconstructed we recommend removing all vegetation and <br />topsoil, if any, and all pavements, aggregate base and any soft or otherwise unsuitable materials <br />from beneath the pavement subgrade. Prior to placing the aggregate base (Class 5) we recommend <br />compacting the subgrade soils to provide a more uniform surface and to identify soft, weak, loose <br />or unstable areas that may require additional subcuts. Backfill, if needed, to attain pavement <br />subgrade elevation can consist of any mineral soil provided it is free of organic material or other <br />deleterious materials but recommend additional fill, if needed, consist of soils similar to the soils <br />at a particular local to reduce the potential for creating areas below the pavement section that <br />could collect water. <br />Granular fill classified as SP or SP-SM should be placed within 65 percent to 105 percent of its <br />optimum moisture content as determined by the standard Proctor. Other fill soils should be <br />placed with moisture contents within a range of 1 percentage point below and 3 percentage points <br />above its optimum moisture content. The upper 3 feet of fill and backfill should be compacted to <br />a minimum of 100 percent of its standard Proctor maximum dry density. <br />Full Depth Reclamation For "Full Depth Reclamation" areas there may be instances where the <br />recommended aggregate base thickness exceeds the existing aggregate base thickness. The <br />preferred method of pavement repair would be to reclaim the existing bituminous, subcut the <br />subgrade, replace the reclaim and add additional aggregate base as needed then construct the <br />bituminous pavement. Subcutting the subgrade may not be feasible or cost effective. As an <br />alternate it may be possible to use a thicker bituminous pavement along with the existing <br />aggregate base or possibly subcutting some of the exiting aggregate base. Using MN/DOT <br />granular equivalencies, one (1) inch of bituminous is equivalent to 2.25 inches of MN/DOT <br />aggregate base. <br />R-Values Laboratory tests to determine the soils Hveem Stabilometer R-Value (R-Value) was <br />beyond the scope of this project. Subgrade soil conditions varied along the alignments and <br />included both clayey and sandy subgrade soil. Table 4 provides a summary of the assumed <br />subgrade R-values. These values were obtained from the MN/DOT, Geotechnical & Pavement <br />Manual (2007). <br />11 <br />