• Substantial completion scheduled in August, 2025 <br />• Final completion scheduled for October, 2025 <br />#20-11 Ramsey Gateway Highway 10 Improvements <br />• Sunfish Lake Blvd grade separations (RR and TH10) are complete and open to traffic <br />• Ramsey Blvd grade separations (RR and TH10) will be constructed in 2025 <br />• Final completion anticipated June 2026 <br />• Project webpage https://www.anokacountymn.gov/3918/Hwy-lORamsey-Blvd-Interchange <br />City of Anoka Improvement Projects <br />Ferry Street / Trunk Highway 47 Grade Separation of BNSF Rail Crossing <br />• City is leading project <br />• $45M in bonds authorized October 2020 <br />Highway 47 Corridor Improvements — Garfield St to Bunker Lk Blvd <br />• Combined with above City -led project <br />• 3-lane design <br />• Received regional solicitation funds for 2027 construction <br />• Permanent signal system at McKinley Street <br />• Construction proposed for 2027 - 2029 <br />Anoka County Improvement Projects <br />• No updates. <br />MnDOT Improvement Projects <br />• No updates. <br />Studies & Items of Interest <br />Wetland 114 P staff updates <br />• Water levels are stable. <br />• Staff continues to monitor water levels and will provide updates as needed. <br />Commercial/Industrial/Residential Developments <br />• Staff can respond to questions as needed. <br />PWC Future Topics Calendar Discussion Items <br />See calendar in next case. <br />Notification: <br />Notification is not required for this case. <br />Time Frame/Observations/Alternatives: <br />Staff estimates up to 10 minutes will be needed for updates and discussion. <br />Recommendation: <br />Staff will offer recommendations on specific items when requested. <br />Outcome/Action: <br />No formal action required. For Committee review and discussion purposes only. <br />