Laserfiche WebLink
o On or around July 8, 2024 (dependent on Contractor's schedule) <br />• Substantial Completion <br />o August 31, 2024 <br />o Final lift of bituminous pavement in -place, concrete repairs compete, boulevard restoration in -place <br />• Final Completion <br />o September 30, 2024 <br />o Verify final turf establishment, project clean up complete <br />Bid Opening <br />On June 4, 2024, a total of three (3) bids were publicly opened and tabulated and the following bids were found <br />to comply with the advertisements for bids. <br />Contractor Base Bid Alternate Bid Total Bid <br />North Valley, Inc. $11478,973.36 $831575.67 $115621549.03 <br />GMH Asphalt Corporation $11533,328.05 $761838.85 $116101166.90 <br />Park Construction Company $11639,857.41 $761867.08 $117161724.49 <br />Engineer's Estimate $1, 462, 680.00 1$82,828.75 1$11545, 508.75 <br />North Valley, Inc. of Nowthen, Minnesota, submitted a total bid in the amount of $1,562,549.03 for the base bid <br />plus alternate bid for said improvements in accordance with the approved plans and specifications and <br />advertisement for bids, and is the lowest responsible bidder. <br />Adding indirect costs in the amount of 14-percent for administrative, engineering, finance, and legal costs brings <br />the total project costs to $1,781,305.89. <br />The low bid is 1.1 percent higher than the engineer's estimate. <br />Bidding was competitive, with all bids being within 10-percent of the low bid. <br />Notification: <br />If a contract for construction is awarded, letters will be mailed to property owners with updates on the project <br />status. The Engineering department maintains City Improvement Project webpages with the most current project <br />information, which will also be updated. <br />Time Frame/Observations/Alternatives: <br />Timeframe: <br />Staff estimates up to 10 minutes will be needed to present this case and respond to questions. <br />Alternatives: <br />Alternative 1 - Motion to adopt Resolution #24-156 accepting bids and awarding a contract for construction for <br />2024 Neighborhood Pavement Overlay Improvements, Improvement Project #24-07 for the base bid plus <br />alternate bid to North Valley, Inc. in the amount of $1,562,549.03. <br />i <br />Alternative 2 - Motion to adopt Resolution #24-156 accepting bids and awarding a contract for construction for <br />2024 Neighborhood Pavement Overlay Improvements, Improvement Project #24-07 for the base bid only to North <br />Valley, Inc. in the amount of $1,478,973.36. <br />Alternative 3 - Motion to deny adoption of Resolution #24-156 at this time. <br />Funding Source: <br />