Timeframe:
<br />Staff estimates up to 10 minutes will be required to present this case and answer questions.
<br />Alternatives:
<br />Alternative #1 — Motion to adopt Resolution #25-071 Accepting Bids and Awarding a Contract to North Valley,
<br />Inc. for the total amount of $1,366,954.38 for High Point Street Reconstructions, Improvement Project #25-05.
<br />Alternative #2 — Motion of other.
<br />Funding Source:
<br />Funding for this improvement is proposed to come from Pavement Management Funds and Storm Water Utility
<br />Funds.
<br />On April 10, 2025 a total of eight (8) bids were received, opened, and tabulated, and the following bids were
<br />found to comply with the advertisement for bids.
<br />Contractor Total Bid
<br />North Valley, Inc. $1,366,954.38
<br />Douglas -Kerr Underground $1,441,046.72
<br />Park Construction Company $1,446,884.05
<br />GMH Asphalt Corporation $1,448,729.90
<br />Knife River Construction $1,519,715.15
<br />Valley Paving, Inc. $1,532,695.33
<br />Asphalt Surface Technologies Corp. $1,541,443.14
<br />Dresel Contracting, Inc. $1,757,749.71
<br />Engineer's Estimate $1, 853, 622.00
<br />The bid of North Valley, Inc. of Nowthen, Minnesota, in the amount of $1,366,954.38 for the total bid of said
<br />improvements in accordance with the approved plans and specifications and advertisement for bids, is the lowest
<br />responsible bidder. Adding indirect costs in the amount of 23-percent brings the total project costs to
<br />$1,681,353.89.
<br />The bid is 26-percent lower than the engineer's estimate, primarily due to lower than anticipated bituminous
<br />paving, and concrete curb and gutter prices.
<br />Funding Source Breakdown:
<br />Funding Source
<br />Pavement Management
<br />Funds
<br />Storm Sewer Utility
<br />Funds
<br />Project Total
<br />Construction Costs Indirect Costs Total Cost
<br />$1,058,076.22 $243,357.53 $1,301,433.75
<br />$308,878.16 $71,041.98 $379,920.14
<br />$1,366,954.38 $314,399.51 $1,681,353.89
<br />The CIP level estimate had a total estimated project cost of $1,986,165, which includes street costs of $1,727,100
<br />and storm sewer costs of $259,065. The final project costs may change depending upon bid prices and actual
<br />construction quantities.
<br />City staff proposes to administer and inspect construction. Plans and specifications were prepared in-house as part
<br />of staff's normal duties.
<br />Recommendation: