<br />§ 3.1.6 Cost Estimates
<br />§ 3.1.6.1 Based on the preliminary design and other design criteria prepared by the Architect, the Construction Manager
<br />shall prepare, for the Architect's review and the Owner's approval, preliminary estimates of the Cost of the Work or the
<br />cost of program requirements using area, volume, or similar conceptual estimating techniques. If the Architect or
<br />Construction Manager suggests alternative materials and systems, the Construction Manager shall provide cost
<br />evaluations of those alternative materials and systems.
<br />§ 3.1.6.2 As the Architect progresses with the preparation of the Schematic Design, Design Development and
<br />Construction Documents, the Construction Manager shall prepare and update, at appropriate intervals agreed to by the
<br />Owner, Construction Manager and Architect, an estimate of the Cost of the Work with increasing detail and refinement.
<br />The Construction Manager shall include in the estimate those costs to allow for the further development of the design,
<br />price escalation, and market conditions, until such time as the Owner and Construction Manager agree on a Guaranteed
<br />Maximum Price for the Work. The estimate shall be provided for the Architect's review and the Owner's approval. The
<br />Construction Manager shall inform the Owner and Architect in the event that the estimate of the Cost of the Work exceeds
<br />the latest approved Project budget, and make recommendations for corrective action.
<br />§ 3.1.6.3 If the Architect is providing cost estimating services as a Supplemental Service, and a discrepancy exists
<br />between the Construction Manager's cost estimates and the Architect's cost estimates, the Construction Manager and the
<br />Architect shall work together to reconcile the cost estimates.
<br />§ 3.1.7 As the Architect progresses with the preparation of the Schematic Design, Design Development and Construction
<br />Documents, the Construction Manager shall consult with the Owner and Architect and make recommendations regarding
<br />constructability and schedules, for the Architect's review and the Owner's approval.
<br />§ 3.1.8 The Construction Manager shall provide recommendations and information to the Owner and Architect regarding
<br />equipment, materials, services, and temporary Project facilities.
<br />§ 3.1.9 The Construction Manager shall provide a staffing plan for Preconstruction Phase services for the Owner's review
<br />and approval.
<br />§ 3.1.10 If the Owner identified a Sustainable Objective in Article 1, the Construction Manager shall fulfill its
<br />Preconstruction Phase responsibilities as required in AIA Document E234TM_2019, Sustainable Projects Exhibit,
<br />Construction Manager as Constructor Edition, attached to this Agreement.
<br />§ 3.1.11 Subcontractors and Suppliers
<br />§ 3.1.11.1 If the Owner has provided requirements for subcontractor procurement in section 1.1.14, the Construction
<br />Manager shall provide a subcontracting plan, addressing the Owner's requirements, for the Owner's review and approval.
<br />§ 3.1.11.2 The Construction Manager shall develop bidders' interest in the Project.
<br />§ 3.1.11.3 The processes described in Article 9 shall apply if bid packages will be issued during the Preconstruction Phase.
<br />§ 3.1.12 Procurement
<br />The Construction Manager shall prepare, for the Architect's review and the Owner's acceptance, a procurement schedule
<br />for items that must be ordered in advance of construction. The Construction Manager shall expedite and coordinate the
<br />ordering and delivery of materials that must be ordered in advance of construction. If the Owner agrees to procure any
<br />items prior to the establishment of the Guaranteed Maximum Price, the Owner shall procure the items on terms and
<br />conditions acceptable to the Construction Manager. Upon the establishment of the Guaranteed Maximum Price, the
<br />Owner shall assign all contracts for these items to the Construction Manager and the Construction Manager shall
<br />thereafter accept responsibility for them.
<br />§ 3.1.13 Compliance with Laws
<br />The Construction Manager shall comply with applicable laws, statutes, ordinances, codes, rules and regulations, and
<br />lawful orders of public authorities applicable to its performance under this Contract, and with equal employment
<br />opportunity programs, and other programs as may be required by governmental and quasi -governmental authorities.
<br />AIA Document A133 — 2019. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. "The American Institute of Architects," "American Institute of Architects,"
<br />"AIA," the AIA Logo, and "AIA Contract Documents" are trademarks of The American Institute of Architects. This document was produced at 10:24:29 ET on
<br />10/16/2025 under Order No.4104243742 which expires on 12/31/2025, is not for resale, is licensed for one-time use only, and may only be used in accordance with
<br />the AIA Contract Documents° Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.
<br />User Notes: (846025776)
<br />
|