<br />CC Work Session
<br />Meeting Date:
<br />10/28/2025
<br />Primary Strategic Plan Initiative: Connect the community through Parks, Trails and Recreational Programming.
<br />Information
<br />Title:
<br />Construction Management Services for The Waterfront Waterplay Project
<br />Purpose/Background:
<br />This work session topic is an opportunity to introduce H+ U Construction to the Council and discuss the administration, 'critical path' aspects, and process and schedule for this complex park project Project
<br />executive and partner, Joe Uhlhorn for H + U Construction will be in attendance at work session. The rest of this topic report text is verbatim, and from the City Council case that is on the October 28th, 2025
<br />regular agenda.
<br />The purpose of this case is to authorize H + U Construction for construction management services for The Waterfront project —and also, to authorize staff and H + U to obtain quotes for mass grading of the site this Fall.
<br />In September, the City issued a Request for Proposal (RFP) for a Construction Manager at Risk (CMAR) with a Guaranteed Maximum Price (GMP) for the water play plaza and associated improvements at The Waterfront. Three
<br />pre -qualified firms were invited to submit proposals, and on October 13th, a panel consisting of city staff and Damon Farber Landscape Architects' representative conducted a thorough interview of two firms, and unanimously
<br />determined that H & U Construction is ideally suited far all the work to be performed in the coming months at the park. H + U will work with the Project Team (City staff and Damon Farber Landscape Architects as the DESIGN TEAM)
<br />to provide pre -construction and construction services including cost and schedule estimating, bidding, and day-to-day construction management for the complex park project. (Damon Farber will still provide all the professional design
<br />services, to include preliminary design, concept design, schematic design, design development, construction documents and construction administration as they were engaged to do earlier this year.)
<br />On October 21s1, 2025, the Public Works Committee recommended to City Council, approval of a contractual agreement with H + U Construction for construction management services for The Waterfront waterplay park improvement
<br />project, in the form of a Construction Manager at Risk agreement.
<br />Attached is the city -issued RFP which provides considerable detail on the scope, tinning, and responsibilities of and for the construction management firm. The second attachment is H + U's proposal, which includes a schedule (work
<br />plan on page 4), which responds to the RFP and challenges of this approximately $5M park project.
<br />Time Frame/Observations/Alternatives:
<br />Observations
<br />As indicated, this case is to authorize a contractual agreement with H + U Construction for construction management services for The Waterfront waterplay park improvement project That standard form is included as the third
<br />attachment, AIA Document A133-2019. This agreement includes an estimated fee schedule consisting of two parts—Preconstruction & Bidding Phase Services, and Construction & Closeout Phase Services.
<br />The Preconstruction & Bidding Phase Services will be a not -to -exceed amount of $50,000, and that scope of work is described in the city -issued RFP, and also reflected in H + U's proposal and Schedule. These preconstruction
<br />services may be summarized as cost estimating, constructability reviews, schedule validation, and value engineering recommendations to ensure delivery of the overall project within the established budget (yet to be determined)
<br />and the July completion schedule.
<br />The Construction & Closeout Phase Services is also included in Document A133-2019 but as an estimate. At the time the preconstruction and bidding services are concluding, H + U will issue a Guaranteed Maximum Price —the
<br />agreement will then return to City Council for acceptance of GMP and corresponding amendment of the agreement. To reiterate, this case authorizes entering into an agreement with H + U Construction for the preconstruction services
<br />for a not -to -exceed amount, which will enable the Design Team (now to include the construction manager) to complete the Plans and Specifications for competitive bidding, at which time H + U will issue the GMP which would then be
<br />considered for acceptance by Council in January, along with final approvals to complete the park project.
<br />For the meeting, staff will present imagery of the considerable progress on plans for the park project, highlight near -term activity of the Design Team —and describe the necessity of performing the mass grading this Fall, to prepare for
<br />full -on construction to begin in February/March 2026.
<br />The estimates in the table below are provided below to communicate the work that has been approved and underway, as well as moving forward, beginning with the 'preconstruction phase wherein H + U Construction will prepare
<br />detailed cost estimates for this project
<br />Preliminary Cast Forecast (informational only) —does not include 0 & M
<br />Activity/Work
<br />111Design, engineering, plans and specifications— Damon Farber Architects
<br />Restroom and support building design, fabrication and delivery (not on -site construction)
<br />ISewer and water service lines
<br />*Construction management services and General Conditions
<br />Mass grading, import class 5 to site
<br />IOwner procured shelters (3) and outdoor furnishings (eliminates consuvction manager fees)
<br />ISAC/WAC, permitting, owner contingency, signage etc.
<br />Construction costs (all trades and scope)
<br />..................................................................................................................
<br />Running budget estimate (preliminary and informational only) all costs totaled over time
<br />II Investment (estimate or
<br />approved amount)
<br />$269k
<br />II $305k
<br />II $148k
<br />II $50k- $700k
<br />$120k
<br />II $1.1M
<br />II $600k
<br />II $2.4M
<br />II $4.6M to $5.6M
<br />Funding Source:
<br />The Constriction Management Services that this case discusses, would be funded by the Park Tmst Fund.
<br />Recommendation:
<br />II
<br />Timeline
<br />Approved June 2025
<br />Approved Sept. 2025
<br />Approved Sept. 2025
<br />Pending: October '25, January '26
<br />Pending: November '25
<br />Pending: Dec. '25/Jan. '26
<br />Pending: Feb. 26/July'26
<br />Pending. Feb. '26/July '26
<br />2025 through 2026
<br />The Public Works Committee and staff recommends entering into a contractual agreement with H + U Construction for construction management services for The Waterfront waterplay park improvement project, in the form of a
<br />Construction Manager at Risk agreement.
<br />Outcome/Action:
<br />This case is informational for an opportunity to meet H + U Construction, and to ask questions associated with the contract and construction plan.
<br />Attachments
<br />RFP for CMAR
<br />H & U Construction proposal
<br />A 133 contract w fee estimate
<br />GMP amendment sample