<br />Councilmember Howell introduced the following resolution and moved for its adoption:  
<br />  
<br />RESOLUTION #24-064  
<br />  
<br />RESOLUTION ACCEPTING BIDS AND AWARDING CONTRACT FOR HALLS  
<br />DOVER ACRES STREET RECONSTRUCTIONS, IMPROVEMENT PROJECT #24-02  
<br />  
<br />WHEREAS, the City of Ramsey proposes to reconstruct the streets within the Halls Dover  
<br />Acres subdivision; and  
<br />  
<br />WHEREAS, pursuant to Ramsey City Council Resolution #23-130, adopted June 13,  
<br />2023, the City Council accepted and awarded the proposal to Bolton & Menk, Inc., for topographic  
<br />survey of the project area; and  
<br />  
<br />WHEREAS, pursuant to Ramsey City Council Resolution #23-129, adopted June 27,  
<br />2023, the City Council accepted and awarded the proposal to Chosen Valley Testing, Inc., for a  
<br />geotechnical report of the project area; and  
<br />  
<br />WHEREAS, pursuant to Ramsey City Council Resolution #23-198, adopted August 22,  
<br />2023, the City Council ordered the City Engineer to prepare plans and specifications for said  
<br />improvements; and  
<br />  
<br />WHEREAS, pursuant to Ramsey City Council Resolution #24-014, adopted on January  
<br />9, 2024, the City Council approved final plans and specification as prepared by the City Engineer  
<br />and authorized advertisement for bids for the same improvements; and  
<br />  
<br />WHEREAS, proposals were received for Construction Staking and As-built Survey of  
<br />$27,144.00 from Bolton and Menk, Inc. for said improvements; and  
<br />  
<br />WHEREAS, bids were advertised in the Anoka Union Herald on January 12 and January  
<br />19, 2024; and   
<br />  
<br />WHEREAS, ten (10) bids were received, opened and tabulated on February 21, 2024, and  
<br />the following bids were found to comply with the approved plans and specifications and  
<br />advertisement for bids; and   
<br />  
<br />Contractor Total Bid  
<br />Dave Perkins Contracting, Inc. $844,919.01  
<br />North Valley, Inc. $877,888.60  
<br />Northwest $964,278.71  
<br />Douglas-Kerr Underground, L.L.C. $995,173.34  
<br />Asphalt Surface Technologies Corp. $995,700.28  
<br />Park Construction Company $1,008,718.76  
<br />Kuechle Underground, Inc. $1,030,696.67  
<br />Northdale Construction Company, Inc. $1,087,714.51  
<br />RL Larson Excavating, Inc. $1,230,335.01  
<br />Meyer Contracting, Inc. $1,268,142.21  
<br />  
<br />
<br />
								 |