Councilmember Riley introduced the following resolution and moved for its adoption:
<br />
<br />RESOLUTION #26-065
<br />
<br />RESOLUTION ACCEPTING BIDS AND AWARDING CONTRACT FOR FLINTWOOD
<br />NDRD
<br />HILLS 2 & 3 STREET RECONSTRUCTIONS, IMPROVEMENT PROJECT #26-05
<br />
<br />WHEREAS, the City of Ramsey proposes to reconstruct the streets within the Flintwood
<br />ndrd
<br />Hills 2 & 3 subdivisions as identified within the 2026 – 2035 Capital Improvement Program;
<br />and
<br />
<br />WHEREAS, pursuant to Ramsey City Council Resolution #25-082, adopted April 22,
<br />2025, the City Council accepted and awarded the proposal to Bolton & Menk Anderson for
<br />topographic survey of the project area in the amount of $3,803.50; and
<br />
<br />WHEREAS, pursuant to Ramsey City Council Resolution #25-101, adopted May 13,
<br />2025, the City Council accepted and awarded the proposal to Independent Testing Technologies,
<br />Inc. for geotechnical survey of the project area in the amount of $6,825.00; and
<br />
<br />WHEREAS, pursuant to Ramsey City Council Resolution #25-139, adopted June 24,
<br />2025, the City Council ordered the City Engineer to prepare plans and specifications for Flintwood
<br />ndrd
<br />Hills 2 & 3 Street Reconstructions, Improvement Project #26-05,
<br />
<br />WHEREAS, pursuant to Ramsey City Council Resolution #26-029, adopted January 27,
<br />2026, the City Council approved final plans and specifications as prepared by the City Engineer
<br />and authorized advertisement for bids for the same improvements; and
<br />
<br />WHEREAS, proposals were received for Construction Staking from Bolton & Menk, Inc.
<br />for said improvements in the amount of $43,110.00; and
<br />
<br />WHEREAS, bids were advertised in the Anoka Union Herald on Friday January 30 and
<br />Friday February 6, 2026; and
<br />
<br />WHEREAS, nine (9) bids were received, opened and tabulated on March 3, 2026, and the
<br />following bids were found to comply with the approved plans and specifications and advertisement
<br />for bids; and
<br />
<br />Contractor Total Bid
<br />North Valley, Inc. $792,282.86
<br />Knife River Corporation – North Central $826,337.15
<br />Omann Brothers Paving, Inc. $865,221.89
<br />Park Construction Company $882,159.00
<br />GMH Asphalt Corporation $922,005.86
<br />Douglas-Kerr Underground, LLC $928,652.75
<br />Asphalt Surface Technologies Corp. $971,032.08
<br />Northwest $1,039,133.00
<br />New Look Contracting, Inc. $1,075,789.25
<br />
<br />
<br />
<br />
|