<br />POLICY BOARD BUSINESS <br /> <br />Case #1: <br /> <br />Wetlands Study Contract Status <br /> <br />Chairperson McDilda asked Coordinator Anderson for an update on the Wetland Study <br />Contract Status. <br /> <br />Coordinator Anderson reminded EPB members that at the previous meeting it was <br />requested that Staff come up with an expected dollar amount for a revised supplemental <br />budget from Westwood Professional Services to cover the remainder of the Wetland <br />Study. He stated that he had been informed that they were 80% to 90% complete with <br />the ground-truthing, which is about accurate. He stated that they have ten wetlands left to <br />conduct MnRAMs on. He stated the budget overage arose when they got ahead of <br />themselves slightly in doing the work versus billing the work. He stated there are <br />approximately 70 wetlands that have been looked at that haven't been paid for yet. <br /> <br />Coordinator Anderson stated the City Council approved a $35,000 budget, but the <br />contract originally called for $33,000. He stated there is a remainder of approximately <br />$1,500.00 budgeted to be spent. He stated that Westwood Professional Services <br />informed him they would provide Staff with a supplemental budget to indicate what was <br />necessary to complete the project. He stated the remaining dollar amount to complete the <br />project wasn't available at the last EPB meeting. He stated the new supplemental budget <br />came back at $39,000 necessary to complete the study in addition to what has already <br />been spent. <br /> <br />Board Member aIds asked what happened to the initial budget proposal. <br /> <br />Coordinator Anderson stated that he has asked for a breakdown of the allocation of <br />dollars spent. He stated that Westwood Professional Services has been asked for a <br />logical explanation as to how it can cost more to study approximately half the wetlands <br />covered under the proposal, as opposed to studying all of the wetlands under the original <br />proposal. He stated that the original proposal gave two options. Option one included all <br />Preserve and Manage 1 wetlands, assuming that approximately 60 wetlands were going <br />to come back in those two categories. The second option was to do all 330 wetlands in <br />the City for a budget of about $67,000. <br /> <br />Coordinator Anderson stated that in comparison to the original proposal of $67,000, the <br />total dollars spent including the supplemental budget will now become approximately <br />$72,000 for just under Y2 of the wetlands. <br /> <br />Board Member aIds asked if Westwood Professional Services has completed more work <br />than they originally intended to do. <br /> <br />Board Member Freeburg asked when Coordinator Anderson had his last communication <br />with Mr. Ron Peterson of Westwood Professional Services. <br /> <br />Environmental Policy Board / September 11, 2006 <br />Page 2 of 13 <br />