A. CONTRACTOR and OWNER recognize that time is of the essence of this Agreement and that OWNER will <br />suffer financial loss if the Work is not completed within the times specified in Paragraph 4.02 above, plus any <br />extensions thereof allowed in accordance with Article 12 of the General Conditions. The parties also <br />recognize the delays, expense, and difficulties involved in proving in a legal or arbitration preceding the <br />actual loss suffered by OWNER if the Work is not completed 011 time. Accordingly, instead of requiring any <br />such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as a penalty), <br />CONTRACTOR shall pay OWNER SIX HUNDRED dollars ($XXXX) for each day that expires after the <br />time specified in Paragraph 4.02 for Completion. <br />ARTICLE 5 - CONTRACT PRICE <br />5.01 OWNER shall pay CONTRACTOR for completion of the Work in accordance with the Contract Documents <br />an amount in current funds at the unit prices as shown on the attached CONTRACTOR'S Bid multiplied by <br />the fmal quantities. As provided in Paragraph 11.03 of the General Conditions, estimated quantities are not <br />guaranteed and determination of actual quantities and classifications are to be made by the ENGINEER in <br />accordance with Paragraph 9.07 of the General Conditions. <br />ARTICLE 6 - PAYMENT PROCEDURES <br />6.01 Submittal and Processing of Payments <br />A. CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the General <br />Conditions. Applications for Payment will be processed by ENGINEER as provided in the General <br />Conditions. <br />6.02 Progress Payments; Retainage <br />A. OWNER shall make progress payments on account of the Contract Price on the basis of CONTRACTOR'S <br />Applications for Payment on or about the first day of each month during performance of the Work as <br />provided in Paragraphs 6.02.A.1 and 6.02.A.2 below. All such payments will be measured by the schedule of <br />values established as provided in Paragraph 2.07.A of the General Conditions (and in the case of Unit Price <br />Work based on the number of units completed) or, in the event there is no schedule of values, as provided in <br />the General Requirements: <br />1. Prior to Completion, progress payments will be made in an amount equal to the percentage indicated <br />below but, in each case, less the aggregate of payments previously made and less such amounts as <br />ENGINEER may determine or OWNER may withhold, including but not limited to liquidated damages, <br />in accordance with Paragraph 14.02 of the General Conditions: <br />6.03 Final Payment <br />a. 95% percent of Work completed (with the balance being retainage). <br />b. 95% percent of cost of materials and equipment not incorporated in the Work (with the balance <br />being retainage). <br />A. Upon final completion and acceptance of the Work in accordance with Paragraph 14.07 of the General <br />Conditions, OWNER shall pay the remainder of the Contract Price as recommended by ENGINEER as <br />provided in said Paragraph 14.07. <br />