NORTII PINE
<br />AGGREGATE' INC,
<br />14551 Lake Drive I Forest Lake, MN 55025 1651,464,6802
<br />To: City Of Ramsey
<br />Address; 7550 Sunwood Drive NW
<br />Ramsey, MN 55303
<br />Project Name: CSAH 83 & 147th Ave Change Order #3
<br />Project Location: Existing Sunwood Drive & Access Drive, Ramsey, MN
<br />Contact:
<br />Phone: (763) 427-1410
<br />Fax: (763) 427-5543
<br />Bid Number: 12-079
<br />Bid Date: 9/21/2012
<br />Item # Item Description Estimated Quantity Unit Unit Price Total Price
<br />A. Alternate 3 ,
<br />1 Remove Existing 2x3 Catch Basin 1,00 EACH $365,00 $365,00
<br />2 Remove Curb & Gutter 32.00 LF . $1.40 $44.80
<br />3 Remove Concrete Crosswalk 84.00 SF $1.80 $151,20
<br />4 Remove Bituminous Pavement 60,00 SY $2.45 $147.00
<br />7 15" RC Pipe Sewer Design 3006 Class IV 69.00 LF $33.00 $2,277.00
<br />8 Connect To Existing Storm Structure 1.00 EACH $2,625.00 $2,625.00
<br />10 Construct Drainage Structure 2x3 Box 1.00 EACH $1,500.00 $1,500.00
<br />11 Construct Drainage Structure DES 48-1020 1,00 EACH $1,600,00 $1,600.00
<br />12 Casting Assembly 1,00 EACH $750,00 $750,00
<br />13 Install Casting 2.00 EACH $150,00 $300,00
<br />14 4" Concrete Sidewalk 167.00 SF $31.05 $5,185,35
<br />`� , 15 B612 Curb & Gutter 32.00 LF $30,60 $979,20
<br />16 8" Concrete Pavement 90,00 SY $76.50 $6,885.00
<br />.*17 B618 Curb & Gutter 67,00 LF $31,60 $2,117.20
<br />Total Price for above A. Alternate 3 Items: $24,926.75
<br />B. Contract Deduct
<br />1 Aggregate Base (CV) Class 5 Modified 2.56 CY ($20.75) ($53,12)
<br />2 Type SP 12,5 Wearing Course Mix (4,C) 2.09 TON ($64,85) ($135.54)
<br />3 Type 12,5 Non Wear Course Mix (4,B) 3.48 TON ($62,75) ($218,37)
<br />4 18" RC Pipe Sewer Design 3006 Class IV 32.00 LF ($30,00) ($960.00)
<br />Total Price for above B. Contract Deduct Items: ($1,367.03)
<br />Notes:
<br />• Price does not Include: Clearing & Grubbing; Site Surveying; Soil Testing; Gravel or Bituminous; Building or Structure Demolition; Hidden or Buried
<br />Debris; Hazardous Materials Removal; Dewatering; Import and/or Export of Dirt; Site Utilities other than those listed above; Moving of Small
<br />Utilities; Any Subsoil Corrections or Trench Borrow; Traffic Control;
<br />o Pricing is based on the engineer(s) plans dated: Change Order #3 dated 9/11/12, shts 4AR, 22AR,25AR,26AR,34AR,2BR,4BR
<br />• Proposal is valid for a period of 30 days from date of proposal.
<br />o Any delays due to incomplete surveying or improper surveying could result in additional charges.
<br />• Price does not include lowering/moving small utilities, If there are utilities not properly represented on plans, price is subject to change.
<br />• All grading needs to be verified by civil engineer as grading is completed.
<br />Payment Terms:
<br />Net due upon receipt of billing, A 1.5% per month service charge will be assessed on unpaid balance.
<br />9/21/2012 5:00:46 AM Page 1 of 2