CHANGE ORDER NO. 1 <br /> TO <br /> CONSTRUCTION CONTRACT FOR <br /> IMPROVEMENT PROJECT 88-13 <br />RUM RIVER TE~%CE SITE IMPROVEMENTS <br /> CITY OF RAMSEY, MINNESOTA <br /> <br />January 4, 1999 Hakanscn Anderson Assoc., Inc. <br /> <br />In accordance with Article 22 of the General Conditions to the <br />ccntract, the contractor has re_cuested in writing to extend the com- <br />pletion date for this ccntract to June 1, 1989. The reason for the <br />request was the late start by the apartment building contractor. The <br />engineer has reviewed the request and found it to be valid. <br />Therefore, the following change shall be made to the contract. <br /> <br />The Contract Period Provided for completion Will be Increased !83 Days. <br />Therefore, the completion date shall be June 1, 1989. <br /> <br />This document will become a supplement to the contract and all pro- <br />visions will apply thereto. <br /> <br />It is understood that this agreement is not valid until the appro- <br />priate signatures are affixed. <br /> <br />CONTRACTOR: W.B. MILLER, iNC. <br /> <br />Title: Date: <br /> <br />ENGINEER: <br /> <br />HAKANSON ANDERSON ASSOC., INC. <br /> <br />Title: Date: <br /> <br />CITY OF RA.~SEY <br /> <br />Title: Date: <br /> <br />File: RA8:!5-6 <br /> <br /> <br />