1. Reference to standards, specifications, Contract Documents and any provision of
<br /> manuals, or codes of any technical any Law or Regulation applicable to the
<br /> society,organization,or association,or to performance of the Work or of any
<br /> Laws or Regulations, whether such standard, specification, manual or code,
<br /> reference be specific or by implication, or of any instruction of any Supplier,
<br /> shall mean the standard, specification, Contractor shall promptly report it to
<br /> manual, code, or Laws or Regulations in Engineer in writing. Contractor shall not
<br /> effect at the time of opening of Bids (or proceed with the Work affected thereby
<br /> on the Effective Date of the Agreement if (except in an emergency as required by
<br /> there were no Bids), except as may be Paragraph 6.16.A)until an amendment or
<br /> otherwise specifically stated in the supplement to the Contract Documents
<br /> Contract Documents. has been issued by one of the methods
<br /> indicated in Paragraph 3.04.
<br /> 2. No provision of any such standard,
<br /> specification, manual or code, or any 3. Contractor shall not be liable to Owner or
<br /> instruction of a Supplier shall be effective Engineer for failure to report any
<br /> to change the duties or responsibilities of conflict, error, ambiguity, or discrepancy
<br /> Owner, Contractor, or Engineer, or any in the Contract Documents unless
<br /> of their subcontractors, consultants, Contractor knew or reasonably should
<br /> agents,or employees from those set forth have known thereof.
<br /> in the Contract Documents. No such
<br /> provision or instruction shall be effective B. Resolving Discrepancies
<br /> to assign to Owner, or Engineer, or any
<br /> of, their Related Entities, any duty or 1. Except as may be otherwise specifically
<br /> authority to supervise or direct the stated in the Contract Documents, the
<br /> performance of the Work or any duty or provisions of the Contract Documents
<br /> authority to undertake responsibility shall take precedence in resolving any
<br /> inconsistent with the provisions of the conflict, error, ambiguity, or discrepancy
<br /> Contract Documents. between the provisions of the Contract
<br /> Documents and:
<br /> 3.03 Reporting and Resolving Discrepancies
<br /> a. the provisions of any standard,
<br /> A. Reporting Discrepancies specification, manual, code, or
<br /> instruction (whether or not
<br /> 1. Contractor's Review of Contract specifically incorporated by
<br /> Documents Before Starting Work. reference in the Contract
<br /> Before undertaking each part of the Documents);or
<br /> Work, Contractor shall carefully study
<br /> and compare the Contract Documents b. the provisions of any Laws or
<br /> and check and verify pertinent figures Regulations applicable to the
<br /> therein and all applicable field performance of the Work (unless
<br /> measurements. Contractor shall promptly such an interpretation of the
<br /> report in writing to Engineer any conflict, provisions of the Contract
<br /> error, ambiguity, or discrepancy which Documents would result in violation
<br /> Contractor may discover and shall obtain of such Law or Regulation).
<br /> a written interpretation or clarification
<br /> from Engineer before proceeding with 3.04 Amending and Supplementing Contract
<br /> any Work affected thereby. Documents
<br /> 2. Contractor's Review of Contract A. The Contract Documents may be amended to
<br /> Documents During Performance of provide for additions,deletions,and revisions
<br /> Work. If, during the performance of the in the Work or to modify the terms and
<br /> Work, Contractor discovers any conflict, conditions thereof by either a Change Order
<br /> error, ambiguity, or discrepancy within or a Work Change Directive.
<br /> the Contract Documents or between the
<br /> Standard General Conditions
<br /> 00 72 00-7