and Contractor, subject to the provisions of approvals that the results certified indicate
<br /> Paragraph 10.05. compliance with the Contract Documents.
<br /> D. When functioning as interpreter and judge E. The limitations upon authority and
<br /> under this Paragraph 9.08, Engineer will not responsibility set forth in this Paragraph 9.09
<br /> show partiality to Owner or Contractor and shall also apply to, the Resident Project
<br /> will not be liable in connection with any Representative,if any,and assistants,if any.
<br /> interpretation or decision rendered in good
<br /> faith in such capacity. ARTICLE 10—CHANGES IN THE WORK;CLAIMS
<br /> 9.09 Limitations on Engineer's Authority and 10.01 Authorized Changes in the Work
<br /> Responsibilities
<br /> A. Without invalidating the Contract and without
<br /> A. Neither Engineer's authority or responsibility notice to any surety, Owner may, at any time
<br /> under this Article 9 or under any other or from time to time, order additions,
<br /> provision of the Contract Documents nor any deletions, or revisions in the Work by a
<br /> decision made by Engineer in good faith Change Order, or a Work Change Directive.
<br /> either to exercise or not exercise such Upon receipt of any such document,
<br /> authority or responsibility or the undertaking, Contractor shall promptly proceed with the
<br /> exercise, or performance of any authority or Work involved which will be performed
<br /> responsibility by Engineer shall create, under the applicable conditions of the
<br /> impose, or give rise to any duty in contract, Contract Documents (except as otherwise
<br /> tort, or otherwise owed by Engineer to specifically provided).
<br /> Contractor, any Subcontractor, any Supplier,
<br /> any other individual or entity,or to any surety B. If Owner and Contractor are unable to agree
<br /> for or employee or agent of any of them. on entitlement to, or on the amount or extent,
<br /> if any, of an adjustment in the Contract Price
<br /> B. Engineer will not supervise,direct,control,or or Contract Times, or both, that should be
<br /> have authority over or be responsible for allowed as a result of a Work Change
<br /> Contractor's means, methods, techniques, Directive, a Claim may be made therefor as
<br /> sequences, or procedures of construction, or provided in Paragraph 10.05.
<br /> the safety precautions and programs incident
<br /> thereto, or for any failure of Contractor to 10.02 Unauthorized Changes in the Work
<br /> comply with Laws and Regulations applicable
<br /> to the performance of the Work.Engineer will A. Contractor shall not be entitled to an increase
<br /> not be responsible for Contractor's failure to in the Contract Price or an extension of the
<br /> perform the Work in accordance with the Contract Times with respect to any work
<br /> Contract Documents. performed that is not required by the Contract
<br /> Documents as amended, modified, or
<br /> C. Engineer will not be responsible for the acts supplemented as provided in Paragraph 3.04,
<br /> or omissions of Contractor or of any except in the case of an emergency as
<br /> Subcontractor, any Supplier, or of any other provided in Paragraph 6.16 or in the case of
<br /> individual or entity performing any of the uncovering Work as provided in Paragraph
<br /> Work. 13.04.13.
<br /> D. Engineer's review of the final Application for 10.03 Execution of Change Orders
<br /> Payment and accompanying documentation
<br /> and all maintenance and operating A. Owner and Contractor shall execute
<br /> instructions, schedules, guarantees, bonds, appropriate Change Orders recommended by
<br /> certificates of inspection,tests and approvals, Engineer covering:
<br /> and other documentation required to be
<br /> delivered by Paragraph 14.07.A will only be 1. changes in the Work which are: (i)
<br /> to determine generally that their content ordered by Owner pursuant to Paragraph
<br /> complies with the requirements of, and in the 10.0l.A, (ii) required because of
<br /> case of certificates of inspections, tests, and acceptance of defective Work under
<br /> Standard General Conditions
<br /> 00 72 00-31
<br />
|