ARTICLE 15—SUSPENSION OF WORK AND construction equipment, and machinery <br /> TERMINATION at the Site, and use the same to the full <br /> extent they could be used by Contractor <br /> 15.01 Owner May Suspend Work (without liability to Contractor for <br /> trespass or conversion), <br /> A. At any time and without cause, Owner may <br /> suspend the Work or any portion thereof for a 2. incorporate in the Work all materials and <br /> period of not more than 90 consecutive days equipment stored at the Site or for which <br /> by notice in writing to Contractor and Owner has paid Contractor but which are <br /> Engineer which will fix the date on which stored elsewhere,and <br /> Work will be resumed. Contractor shall <br /> resume the Work on the date so fixed. 3. complete the Work as Owner may deem <br /> Contractor shall be granted an adjustment in expedient. <br /> the Contract Price or an extension of the <br /> Contract Times, or both, directly attributable C. If Owner proceeds as provided in Paragraph <br /> to any such suspension if Contractor makes a 15.02.13, Contractor shall not be entitled to <br /> Claim therefor as provided in Paragraph receive any further payment until the Work is <br /> 10.05. completed. If the unpaid balance of the <br /> Contract Price exceeds all claims, costs, <br /> 15.02 Owner May Terminate for Cause losses,and damages(including but not limited <br /> to all fees and charges of engineers,architects, <br /> A. The occurrence of any one or more of the attorneys, and other professionals and all <br /> following events will justify termination for court or arbitration or other dispute resolution <br /> cause: costs) sustained by Owner arising out of or <br /> relating to completing the Work, such excess <br /> 1. Contractor's persistent failure to perform will be paid to Contractor. If such claims, <br /> the Work in accordance with the Contract costs, losses, and damages exceed such <br /> Documents(including,but not limited to, unpaid balance, Contractor shall pay the <br /> failure to supply sufficient skilled difference to Owner. Such claims, costs, <br /> workers or suitable materials or losses, and damages incurred by Owner will <br /> equipment or failure to adhere to the be reviewed by Engineer as to their <br /> Progress Schedule established under reasonableness and, when so approved by <br /> Paragraph 2.07 as adjusted from time to Engineer, incorporated in a Change Order. <br /> time pursuant to Paragraph 6.04); When exercising any rights or remedies under <br /> this Paragraph Owner shall not be required to <br /> 2. Contractor's disregard of Laws or obtain the lowest price for the Work <br /> Regulations of any public body having performed. <br /> jurisdiction; <br /> D. Notwithstanding Paragraphs 15.02.13 and <br /> 3. Contractor's disregard of the authority of 15.02.0, Contractor's services will not be <br /> Engineer;or terminated if Contractor begins within seven <br /> days of receipt of notice of intent to terminate <br /> 4. Contractor's violation in any substantial to correct its failure to perform and proceeds <br /> way of any provisions of the Contract diligently to cure such failure within no more <br /> Documents. than 30 days of receipt of said notice. <br /> B. If one or more of the events identified in E. Where Contractor's services have been so <br /> Paragraph 15.02.A occur, Owner may, after terminated by Owner,the termination will not <br /> giving Contractor (and surety) seven days affect any rights or remedies of Owner against <br /> written notice of its intent to terminate the Contractor then existing or which may <br /> services of Contractor: thereafter accrue.Any retention or payment of <br /> moneys due Contractor by Owner will not <br /> 1. exclude Contractor from the Site, and release Contractor from liability. <br /> take possession of the Work and of all <br /> Contractor's tools, appliances, <br /> Standard General Conditions <br /> 00 72 00-46 <br />