F. If and to the extent that Contractor has Engineer fails to act on any Application for <br /> provided a performance bond under the Payment within 30 days after it is submitted, <br /> provisions of Paragraph 5.0l.A, the or (iii) Owner fails for 30 days to pay <br /> termination procedures of that bond shall Contractor any sum finally determined to be <br /> supersede the provisions of Paragraphs due, then Contractor may, upon seven days <br /> 15.02.13,and 15.02.C. written notice to Owner and Engineer, and <br /> provided Owner or Engineer do not remedy <br /> 15.03 Owner May Terminate For Convenience such suspension or failure within that time, <br /> temninate the Contract and recover from <br /> A. Upon seven days written notice to Contractor Owner payment on the same terms as <br /> and Engineer, Owner may,without cause and provided in Paragraph 15.03. <br /> without prejudice to any other right or remedy <br /> of Owner, terminate the Contract. In such B. In lieu of terminating the Contract and without <br /> case, Contractor shall be paid for (without prejudice to any other right or remedy, if <br /> duplication of any items): Engineer has failed to act on an Application <br /> for Payment within 30 days after it is <br /> 1. completed and acceptable Work executed submitted, or Owner has failed for 30 days to <br /> in accordance with the Contract pay Contractor any sum finally determined to <br /> Documents prior to the effective date of be due, Contractor may, seven days after <br /> temlination,including fair and reasonable written notice to Owner and Engineer, stop <br /> suns for overhead and profit on such the Work until payment is made of all such <br /> Work; amounts due Contractor, including interest <br /> thereon. The provisions of this Paragraph <br /> 2. expenses sustained prior to the effective 15.04 are not intended to preclude Contractor <br /> date of termination in performing from making a Claim under Paragraph 10.05 <br /> services and furnishing labor, materials, for an adjustment in Contract Price or <br /> or equipment as required by the Contract Contract Times or otherwise for expenses or <br /> Documents in connection with damage directly attributable to Contractor's <br /> uncompleted Work, plus fair and stopping the Work as permitted by this <br /> reasonable suns for overhead and profit Paragraph. <br /> on such expenses; <br /> ARTICLE 16—DISPUTE RESOLUTION <br /> 3. all claims, costs, losses, and damages <br /> (including but not limited to all fees and 16.01 Methods and Procedures <br /> charges of engineers, architects, <br /> attorneys, and other professionals and all A. Either Owner or Contractor may request <br /> court or arbitration or other dispute mediation of any Claim submitted to Engineer <br /> resolution costs)inured in settlement of for a decision under Paragraph 10.05 before <br /> terminated contracts with Subcontractors, such decision becomes final and binding. The <br /> Suppliers,and others;and mediation will be governed by the <br /> Construction Industry Mediation Rules of the <br /> 4. reasonable expenses directly attributable American Arbitration Association in effect as <br /> to termination. of the Effective Date of the Agreement. The <br /> request for mediation shall be submitted in <br /> B. Contractor shall not be paid on account of writing to the American Arbitration <br /> loss of anticipated profits or revenue or other Association and the other party to the <br /> economic loss arising out of or resulting from Contract. Timely submission of the request <br /> such termination. shall stay the effect of Paragraph 10.05.E. <br /> 15.04 Contractor May Stop Work or Terminate B. Owner and Contractor shall participate in the <br /> mediation process in good faith. The process <br /> A. If,through no act or fault of Contractor,(i)the shall be concluded within 60 days of filing of <br /> Work is suspended for more than 90 the request. The date of termination of the <br /> consecutive days by Owner or under an order mediation shall be determined by application <br /> of court or other public authority, or (ii) of the mediation rules referenced above. <br /> Standard General Conditions <br /> 00 72 00-47 <br />