pouring new curb and gutter. The negotiated cost for this work is $50 per linear foot, which is about $9 per foot <br />more than the original bid price for curb and gutter removal and replacement. Staff believes this is a reasonable cost <br />considering the additional work involved. This work results in a project cost increase of $26,700. <br />It was also discovered during construction that a catch basin needed to be reconstructed by hand using block and <br />mortar instead of using a prefabricated concrete catch basin as specified in the plans. This was due to the existing <br />elevations and geometry of the storm sewer pipes. This additional work results in an increased project cost of $1,800 <br />($4,000 for the 48" hand built catch basin minus $2,200 for the prefabricated catch basin that will no longer be paid <br />for through the contract). <br />It is also worth noting that during construction it was discovered that five areas of Sunwood Drive were constructed <br />with less than 2-inches of bituminous pavement. Therefore, approximately 1'/2" of the existing aggregate base was <br />removed in each area and approximately 1'/2" of base bituminous pavement was placed on top of the remaining <br />compacted aggregate base to provide a minimum of 3'/2" of bituminous pavement along these segments of Sunwood <br />Drive. The additional pavement tonnage required to complete this work is proposed to be paid using the existing <br />bituminous pavement pay item, which the contractor approves of. <br />The extra work addressed within Change Order #1 results in a total project cost increase of $28,500, though the total <br />cost of the Change Order equals $30,700. <br />Notification: <br />No notifications are required for this case. <br />Observations/Alternatives: <br />Observations: <br />These additional project costs will not impact the proposed assessments for the three benefiting properties. <br />Alternatives: <br />Alternative #1 — Motion to adopt Resolution #16-09-173 approving Change Order #1 for 2016 Mill and Overlay <br />Improvements; Improvement Project 16-00 Division B. <br />Alternative #2 — Motion to deny adoption of Resolution #16-09-173 at this time. <br />Funding Source: <br />Additional funding associated with Change Order #1, which totals $30,700, is proposed to be paid from the Street <br />Overlay Bonds that were secured for this project in the amount of $300,000. Total project cost, including Change <br />Order #1 and 14% indirect costs covering administrative, engineering, finance and legal fees, is estimated at <br />$232,783.68 which is significantly less than the amount bonded for this project. <br />Recommendation: <br />Staff recommends approving Alternative #1. <br />Action: <br />Motion to adopt Resolution #16-09-173 approving Change Order #1 for 2016 Mill and Overlay Improvements; <br />Improvement Project 16-00 Division B. <br />Attachments <br />Handmade CB invoice <br />Change Order 1 <br />Form Review <br />