Final Site Plan Reivw - Comer Retail Building Town Center 3rd Addition <br />October 7,. 2004 <br />Page 4 of 8 <br /> <br />Sheet Specific Comments . <br />· All utility pages - Continuation references are not correct. Review and revise all <br /> affected sheets. <br />· Show all crossing pipes in profile views.' <br />· Page 36 View 9.2 - Move the hydrant on the southeast comer of the grocery, building to <br /> the east side of the driveway. It must be outside the potential impact zone if 'the wall <br /> were to fall over during a fire. Profile view shows plan view pipes, <br />· Page 37 View2 Move hydrant from south of west side of island adjacent to <br /> building. <br />· Page 38 Submit diagram for hydrant and line between CBMH 16 and CBMH 17. <br />· Page 40 Submit diagram for h, ydrant near CBMH 5. <br />· Page 43 Update finished grade in profile view. <br />· Page 64 Show watermain in.profile. Show raw water line that will be installed by <br /> others also. <br /> <br />The RTC development will require additional water supply wells. This was anticipated and a lot <br />was platted on the east side of Zeolite Street for a fi~ture well. 'An exploratory well has been <br />developed on the lot and the plans for pipe to connect this well with the city water distribzttion <br />system have been issued for construction. The proposed gas station on the site is within the well <br />head protection area for this future well. Gas Stations are not explicitly prohibited in well head <br />protection areas, however additional protection measures are required for the underground <br />storage tanks and dispensing areas. Plans.Jbr these additional controls must be submitted to the <br />city flbr approval. Relocation of the well has been suggested by the developer. This may be <br />acceptable to the city if ct suitable site for the new well can be found. The developer will be <br />responsible for reimbursing the city expenditures to date on the cztrrent well sire and <br />reimbursing the city for the cost of pipe installed but not z~sed to connect to the original well. <br /> <br />· Coordinates are shown on the current plans. The basis datum for these coordinates <br /> must be specified, several conflicting coordinate systems have been used on this <br /> project to date. <br />· The buildings along Sunwood and Zeolite are permitted up to the right of way. Stoops <br /> for doors should be must be kept inside the property, stoops protruding into the right <br /> of way interfere with the small utilities. <br /> <br />Sheet Specific Comments <br />· Page 23 Call out "Concrete aprons per city standard" <br /> Page 48 Section 2. Note 2- Joint lines based on radius point. How are contractors to <br /> determine this radius'? <br />· Page 62 Railings are r~tuired on all retaining walls over 3.5 ft. Add railings to the <br /> sections. <br /> <br /> <br />