If Council accepts the bids and awards a contract for construction of the improvements, letters will be mailed to
<br />property owners with updates on the project status. Engineering Staff maintains City Improvement webpages with
<br />the most current project information, this can be found on the City website, Engineering department page.
<br />Time Frame/Observations/Alternatives:
<br />Alternative #1 — Motion to adopt Resolution #23-081 awarding a contract for 161 st Avenue Reconstruction,
<br />Improvement Project #23-01.
<br />Alternative #2 — Motion of other.
<br />Funding Source:
<br />Funding for this improvement is proposed to come from MSA funds, Stormwater Utility Funds, Sanitary Sewer
<br />Utility Funds, Water Utility Funds, and Park Improvement Trust Funds. City Staff applied for the State Active
<br />Transportation Grant to help offset construction costs of the trail, but were unsuccessful at obtaining the grant
<br />award.
<br />Bids were advertised in the Anoka Union Herald and in Finance and Commerce on March 17 and March 24,
<br />2023. On April 19, 2023 a total of nine (9) bids were received, opened, and tabulated, and the following bids
<br />were found to comply with the advertisement for bids.
<br />Contractor Total Bid
<br />Northern Lines Contracting, Inc. $1,244,237.29
<br />Douglas -Kerr Underground, L.L.0 $1,247,068.00
<br />Dave Perkins Contracting Inc. $1,320,396.06
<br />Kuechle Underground Inc. $1,360,552.54
<br />Northdale Construction Company $1,471,552.39
<br />Park Construction Company $1,484,609.60
<br />Asphalt Surface Technologies Corp. $1,549,305.25
<br />RL Larson Excavating Inc. $1,593,708.10
<br />Meyer Contracting Inc. $1,607,498.32
<br />Engineer's Estimate $1, 600, 511.75
<br />The bid of Northern Lines Contracting, Inc. of Hanover, Minnesota, in the amount of $1,244,237.29 for the total
<br />bid construction of said improvements in accordance with the approved plans and specifications and
<br />advertisement for bids, is the lowest responsible bidder. Adding indirect costs in the amount of 23-percent brings
<br />the total project costs to $1,530,411.87.
<br />The low bid is 22-percent less than the engineer's estimate, primarily due to lower than anticipated bituminous
<br />and excavation costs.
<br />Funding Source Breakdown:
<br />Funding Source Construction Costs Indirect Costs Total Costs
<br />Municipal State Aid $551,840.87 $126 923.40 $678 764.27
<br />(MSA) Funds '
<br />Park Improvement Trust $134,023.89 $30,825.49 $164 849.38
<br />Funds '
<br />Stormwater Utility Funds p$283,603.53 $65,228.81 $348,832.34
<br />Water Utility Funds $133,693.50 $30,447.37 $173,522.87
<br />Sanitary Sewer Utility $141,075.50 $32,447.37 $173 522.87
<br />Funds '
<br />Project Total $1,244,237.29 $286,174.58 $1,530,411.87
<br />
|