establishing turf.
<br />A total of ten (10) bids were publicly received, opened and tabulated on August 4, 2023, and the following bids
<br />were found to comply with the approved plans and specifications and advertisements for bids.
<br />Company Bid
<br />Enebak Construction Company $4,197,240.34
<br />Northern Lines Contracting $4,645,588.10
<br />S.M. Hentges & Sons, Inc. $4,844,964.99
<br />Fehn Companies, Inc. $4,925,721.40
<br />North Pine Aggregate, Inc. $4,930,786.05
<br />Kevitt Excavating $5,474,246.20
<br />RL Larson Excavating, Inc. $6,166,010.15
<br />Frattalone Companies $7,459,251.05
<br />The Mathiowetz Construction $7,594,160.46
<br />Meyer Contracting, Inc. $7,822,784.20
<br />Engineer's Estimate $8, 571, 540.50
<br />The bid of Enebak Construction Company in the amount of $4,197,240.34 for the total bid for construction of the
<br />improvements in accordance with the approved plans and specifications and advertisements for bids, was the
<br />lowest responsible bid received. Upon adopting Resolution #23-176, a construction contract will be awarded to
<br />Enebak Construction Company in the amount of $4,197,240.34.
<br />Notification:
<br />Bids were advertised in the Anoka Union Herald on Friday, July 14th, and Friday, July 21 st, 2023.
<br />Time Frame/Observations/Alternatives:
<br />Observations:
<br />Design and plan preparation for the three segments of Zeolite Street, Center Street, and Ramsey Parkway
<br />identified above are underway and will be complete this Fall. Construction of these street segments can then
<br />occur in 2024, or later.
<br />The next Council action that will be requested will be to approve plans and specifications and authorize bids for
<br />the reconstruction of Zeolite Street between Sunwood Drive and Bunker Lake Boulevard, as well as the
<br />construction of Ramsey Parkway between Zeolite Street and the roundabout at the intersection of Sunwood Drive
<br />and 147th Avenue, which were identified as the highest priority street segments by consensus of the City Council
<br />on July 18, 2023, during the special City Council work session. This request is anticipated to be presented to
<br />Council this Fall/Winter after final construction plans for these street segments are complete.
<br />Zeolite Street will remain closed to traffic during the COR mass grading operations.
<br />Alternatives:
<br />Alternative #1: Adopt Resolution #23-176 accepting bids and awarding a contract for construction for
<br />Improvement Project #23-20, COR Mass Grading, to Enebak Construction Company in the amount of
<br />$4,197,240.34.
<br />Alternative #2: Motion of other.
<br />Funding Source:
<br />
|