Memorandum <br /> January 12, 2022 <br /> Page 2 <br /> to predict future trends with the construction market, waiting to rebid allows time for supply chain and <br /> pandemic issues possibly work themselves out and influence costs to a lesser degree. <br /> It is also recommended to evaluate the economics of utilizing ductile iron pipe (DIP)as material alternate <br /> for areas of the project associated with open cut installation of the water main along with the feasibility of <br /> increasing the amount of open cut pipe installation to evaluate any additional cost savings. <br /> Also note, DIP pipe has a current lead time of approximately 30 weeks. If it is determined DIP pipe will be <br /> included in the rebid, lead times will need to be evaluated at that time to allow a bid opening date to be <br /> set that allows for timely delivery of pipe materials. <br /> ces <br /> c: file <br /> x:\pt\r\ramsy\159783\6-bid-const\elevated bid costs memo.docx <br />