Laserfiche WebLink
c� <br /> nEs <br /> www.ae2s.coni <br /> March 1, 2024 <br /> Bruce Westby <br /> City of Ramsey <br /> 7550 Sunwood Drive NW <br /> Ramsey, MN 55303 <br /> Re: Water Treatment Plant—Construction Contingency Expense No.3 <br /> Dear Mr. Westby: <br /> AE2S continues to oversee the construction of the City of Ramsey's new WTP. Magney has completed a <br /> majority of the concrete pours at the subgrade level of the Water Treatment Plant along with both the <br /> backwash tank and clearwell base slabs. Our engineering team has continued to coordinate with Magney <br /> and further refine the installation details of other pieces of equipment. Through those investigations we <br /> have identified some items that will require adjustments. This letter is intended to outline those adjustments <br /> and summarize the current project budget in order for the City to fully understand the status of the project. <br /> Basis for of Construction Contingency Expenses: <br /> Currently ten(10)requests for pricing(RFP)have been submitted to Magney. A full list of those requests <br /> are shown below. To date AE2S has received pricing back on nine(9)of the RFP's, and seven(7)separate <br /> proposals. We would like to move forward and process Construction Contingency Expense No. 3, which <br /> will include price Proposal No. 010, 012, 013, 014, 015, and 016. If the Contractor would like to include a <br /> request for extension as a result of these changes,a formal Change Order request will be issued at a different <br /> time. <br /> Proposal RFP Description Total Cost Required Status 91 <br /> No. No. 01 <br /> 001 001 Mixing Pumps Pipe Upsizing $511287.38 Y Approved— <br /> Construction Contingency Expense 1 <br /> 002 003 Admin Ceiling Grid Color $21609.25 N Approved— <br /> Construction Contingency Expense 1 <br /> 003 Building Permit $621887 28 Y Approved— <br /> Reimbursement Construction Contingency Expense 2 <br /> 004 002 Upsizing Air Exchange in Plate $16,580.02 N Approved— <br /> Settler Room Construction Contingency Expense 2 <br /> 005 Storm and Plumbing Updates $22,550.28 Y Approved— <br /> Construction Contingency Expense 1 <br /> 006 005 Flowable Fill - N Rejected <br /> 007 004 Blower Pipe Upsizing $55,230.60 Y Approved— <br /> Construction Contingency Expense 2 <br /> 008 Groundbreaking Signage $956.12 Y Approved— <br /> Reimbursement Construction Contingency Expense 2 <br /> 009 Prevailing Wages $7941153.71 Y Approved— <br /> Chan e Order 01 <br /> O10 007 Backwash Supply Piping $31068.77 Y Pending <br /> Modifications <br /> Oil FO NO.2 Electrical TBD Under Review <br /> Modifications <br /> 012 Accordion Folding Security $101010.85 N Pending <br /> Door <br /> 013 008 Jet Mixing System Pump $161834.33 Y Pending <br /> Modifications <br /> 014 009 Backwash Tank Overflow $L534.38 Y Pending <br /> Advanced Engineering and Environmental Services, Inc. <br /> 6901 East Fish Lake Road,Suite 184 • Water Tower Place Business Center • Maple Grove, MN 55369 • 763-463-5036 <br />