Exhibit
<br /> of the Work or(2)the initial date of Substantial Completion identified in the agreement between the Owner and
<br /> Contractor,whichever is earlier, shall be compensated as Additional Services to the extent the Architect incurs
<br /> additional cost in providing those Construction Phase Services.
<br /> §4.2.5 If the services covered by this Agreement have not been completed within ( )months of the date of this
<br /> Agreement,through no fault of the Architect,extension of the Architect's services beyond that time shall be
<br /> compensated as Additional Services.
<br /> ARTICLE 5 OWNER'S RESPONSIBILITIES
<br /> §5.1 Unless otherwise provided for under this Agreement,the Owner shall provide information in a timely manner
<br /> regarding requirements for and limitations on the Project,including a written program,which shall set forth the
<br /> Owner's objectives; schedule;constraints and criteria,including space requirements and relationships; flexibility;
<br /> expandability;special equipment; systems; and site requirements.
<br /> §5.2 The Owner shall establish the Owner's budget for the Project,including(1)the budget for the Cost of the Work
<br /> as defined in Section 6.1; (2)the Owner's other costs;and, (3)reasonable contingencies related to all of these costs.
<br /> The Owner shall update the Owner's budget for the Project as necessary throughout the duration of the Project until
<br /> final completion. If the Owner significantly increases or decreases the Owner's budget for the Cost of the Work,the
<br /> Owner shall notify the Architect.The Owner and the Architect shall thereafter agree to a corresponding change in
<br /> the Proj ect's scope and quality.
<br /> §5.3 The Owner shall identify a representative authorized to act on the Owner's behalf with respect to the Project.
<br /> The Owner shall render decisions and approve the Architect's submittals in a timely manner in order to avoid
<br /> unreasonable delay in the orderly and sequential progress of the Architect's services.
<br /> §5.4 The Owner shall furnish surveys to describe physical characteristics,legal limitations and utility locations for
<br /> the site of the Project, and a written legal description of the site.The surveys and legal information shall include, as
<br /> applicable,grades and lines of streets, alleys,pavements and adjoining property and structures; designated wetlands;
<br /> adjacent drainage; rights-of-way,restrictions, easements,encroaclunents,zoning,deed restrictions,boundaries and
<br /> contours of the site;locations,dimensions,and other necessary data with respect to existing buildings, other
<br /> improvements and trees; and information concerning available utility services and lines,both public and private,
<br /> above and below grade,including inverts and depths.All the information on the survey shall be referenced to a
<br /> Project benchmark.
<br /> §5.5 The Owner shall furnish services of geotechnical engineers,which may include test borings,test pits,
<br /> determinations of soil bearing values,percolation tests,evaluations of hazardous materials, seismic evaluation,
<br /> ground corrosion tests and resistivity tests,including necessary operations for anticipating subsoil conditions,with
<br /> written reports and appropriate recommendations.
<br /> §5.6 The Owner shall provide the Supplemental Services designated as the Owner's responsibility in Section 4.1.1.
<br /> §5.7 If the Owner identified a Sustainable Objective in Article 1,the Owner shall fulfill its responsibilities as
<br /> required in AIA Document E244T11'—2417, Sustainable Projects Exhibit,attached to this Agreement.
<br /> §5.8 The Owner shall coordinate the services of its own consultants with those services provided by the Architect.
<br /> Upon the Architect's request,the Owner shall furnish copies of the scope of services in the contracts between the
<br /> Owner and the Owner's consultants.The Owner shall furnish the services of consultants other than those designated
<br /> as the responsibility of the Architect in this Agreement,or authorize the Architect to furnish them as an Additional
<br /> Service,when the Architect requests such services and demonstrates that they are reasonably required by the scope
<br /> of the Project. The Owner shall require that its consultants and contractors maintain insurance,including
<br /> professional liability insurance,as appropriate to the services or work provided.
<br /> §5.9 The Owner shall furnish tests,inspections and reports required by law or the Contract Documents,such as
<br /> structural,mechanical, and chemical tests,tests for air and water pollution, and tests for hazardous materials.
<br /> §5.10 The Owner shall furnish all legal,insurance and accounting services,including auditing services,that may be
<br /> reasonably necessary at any time for the Project to meet the Owner's needs and interests.
<br /> AIA Document B101 TM—2017.Copyright©1974,1978.1987,1997,2007 and 2017 by The American Institute of Architects.All rights reserved.WARNING:
<br /> In it. This AIA° Document is protected by U.S.Copyright Law and International Troatios.Unauthorized reproduction or distribution of this AIA Document,
<br /> 14
<br /> or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law.This
<br /> document was produced by AIA software at 14:48:43 on 12/12/2017 under Order No.3422979013 which expires on 11/08/2018,and is not for resale.
<br /> User Notes: (3139ADA1 D)
<br />
|