SW PPP_1_PROJ_INFO_MAP dwg 8/20/2024 4 06 29 PM
<br />STORMWATER
<br />POLLUTION PREVENTION
<br />PLAN (SWPPP)
<br />Rivers Bend Pond -2024
<br />CITY OF Ramsey
<br />Anoka COUNTY, MINNESOTA
<br />PROJECT LOCATION
<br />RESPONSIBLE PARTIES:
<br />The Contractor and Owner will be joint applicants under the MPCA's General Stormwater Permit for Construction Activity as required
<br />by the National Pollutant Discharge Elimination System (NPDES) Phase II program.
<br />The Contractor shall provide one or more trained Construction SWPPP Manager(s) knowledgeable and experienced in the application
<br />of erosion prevention and sediment control BMPs that will oversee the implementation of the SWPPP, and the installation, inspection
<br />and maintenance of the erosion prevention and sediment control BMPs.
<br />A Construction SWPPP Manager must be available for an on -site inspection within 72 hours upon request by the MPCA.
<br />COMPANY
<br />CONTACT PERSON
<br />PHONE
<br />OWNER:
<br />City of Ramsey
<br />Bruce Westby, PE
<br />763-433-9825
<br />SWPPP DESIGNER:
<br />Bolton & Menk, Inc.
<br />Timothy Haugo
<br />763-433-2851
<br />CONTRACTOR:
<br />TBD
<br />TBD
<br />TBD
<br />CONSTRUCTION SWPPP MANAGER:
<br />TBD
<br />TBD
<br />TBD
<br />PARTY RESPONSIBLE FOR LONG TERM O&M:
<br />City of Ramsey
<br />Bruce Westby, PE
<br />763-433-9825
<br />The SWPPP Designer, Construction SWPPP Manager, and BMP Installer must have appropriate training. Documentation showing
<br />training commensurate with the job duties and responsibilities is required to be included in the SWPPP prior to any work beginning on
<br />the site. Training documentation for the SWPPP Designer is included on the Narrative sheet. The Contractor shall attach training
<br />documentation to this SWPPP for the Construction SWPPP Manager and BMP Installer prior to the start of construction. This
<br />information shall be kept up to date until the project NOT is filed.
<br />ADDITIONAL COMPENSATION
<br />Payment for all work associated with Erosion and Sediment Control shall be as described in the Project Manual. Unless otherwise
<br />authorized by the Owner no additional payment shall be made for any work required to administer and maintain the site erosion and
<br />sediment control in compliance with the Minnesota Pollution Control Agency (MPCA) - General Stormwater Permit for Construction
<br />Activity (MN R100001) including but not limited to inspection, maintenance, and removal of BMPs or addition of BMPs to
<br />accommodate Contractor phasing.
<br />DOCUMENT RETENTION
<br />Permittees must make the SWPPP, including all inspection reports, maintenance records, training records and other information
<br />required by this permit, available to federal, state, and local officials within three (3) days upon request for the duration of the permit
<br />and for three (3) years following the NOT.
<br />GENERAL STORMWATER DISCHARGE REQUIREMENTS
<br />All requirements listed in Section 5.1 of the Permit for the design of the permanent stormwater management system and discharge
<br />have been included in the preparation of this SWPPP. These include but are not limited to:
<br />1. The expected amount, frequency, intensity, and duration of precipitation.
<br />2. The nature of stormwater runoff and run-on at the site
<br />3. Peak flow rates and stormwater volumes to minimize erosion at outlets and downstream channel and stream bank erosion.
<br />4. The range of soil particle sizes expected to be present on the site.
<br />Permanent stormwater treatment systems for this project have been designed in accordance with the guidance in the MN Stormwater
<br />Manual in place at the time of bidding. Copies of the design information and calculations are part of this SWPPP and will be provided in
<br />digital format upon written request to the Engineer.
<br />LEGEND
<br />PROJECT AREAS:
<br />Total Project Size (disturbed area),
<br />Existing area of impervious surface =
<br />Post construction area of impervious surface =
<br />Total new impervious surface area created =
<br />PROJECT LOCATION
<br />1-MILE BOUNDARY
<br />IMPAIRED, SPECIAL OR PROTECTED WATERS
<br />NATIONAL WETLANDS INVENTORY
<br />RECEIVING WATERS
<br />2.8
<br />0
<br />0
<br />0
<br />Planned Construction Start Date: 9/15/2024
<br />Estimated Construction Completion Date: 11/15/2024
<br />ACRES
<br />ACRES
<br />ACRES
<br />ACRES
<br />PERMANENT STORMWATER MANAGEMENT SYSTEM:
<br />Type of storm water management used if more than 1 acre of new impervious surface is created:
<br />1
<br />Wet Sedimentation Basin
<br />Infiltration/Filtration
<br />Regional Pond
<br />Permanent Stormwater Management Not Required
<br />PROJECT LOCATION:
<br />COUNTY
<br />TOWNSHIP
<br />RANGE
<br />SECTION
<br />LATITUDE
<br />LONGITUDE
<br />ANOKA
<br />T32N
<br />R25W
<br />25
<br />45.22821°
<br />-93.39473°
<br />BMP SUMMARY
<br />QUANTITY
<br />UNIT
<br />STORM DRAIN INLET PROTECTION
<br />5
<br />EACH
<br />ROLLED EROSION PREVENTION CATEGORY 20
<br />8,500
<br />SQYD
<br />SEEDING MIXTURE 35-241
<br />70
<br />POUND
<br />SILT FENCE MACHINE SLICED
<br />1,800
<br />LIN FT
<br />RIP RAP CLASS III
<br />50
<br />CU YD
<br />STABILIZED CONSTRUCTION EXIT
<br />1
<br />EACH
<br />DESCRIPTION OF CONSTRUCTION ACTIVITIES AND STORMWATER MANAGEMENT:
<br />Construction activities include: Site grading, sanitary sewer and water main extensions, temporary
<br />erosion and sediment control, and permanent stabilization.
<br />Storm water currently from the urbanized and undeveloped area is currently being routed to catch basins
<br />located along 142nd Ave NW and Xkimo St. NW and flow through storm drains into an existing pond
<br />located within Rivers Band park. The existing pond is located south of 142nd Ave NW and Waco st. NW
<br />intersection. The outlet of the pond is Rum River. The current pond size is in adequate to treat the current
<br />impervious area.
<br />After construction is complete storm water will be managed in a different pond area. The water will be
<br />routed through the catch basins located on 142nnd Ave. NW and Xkimo ST. NW and then routed through
<br />storm drains to the new biofiltration pond. First entering a wet sedimentation basin with a capacity of
<br />74,000 cubic feet, 5 feet deep, then entering the biofiltration basin. The pond will have a treatment
<br />capacity of 148,795 cubic feet.
<br />This project includes the following stormwater management BMPs: Biofiltration and wet sedimentation.
<br />1-MILE
<br />!BOUNDARY
<br />J
<br />ti
<br />s 4� PROJECT
<br />Gr11 I LOCATION
<br />RECEIVING
<br />WATERS
<br />1500
<br />3000
<br />SCALE
<br />FEET
<br />RECEIVING WATERS:
<br />Receiving waters, including surface water, wetlands, Public Waters, and stormwater ponds, within 1-mile of the project boundary are identified on the
<br />USGS 7.5 min quad map above. Receiving waters that are impaired, the impairment, and WLA are listed as follows. All specific BMPs relative to
<br />construction activities listed in the permit for special prohibited, restricted, or impaired have been incorporated into this plan. All specific BMPs listed in
<br />approved TMDLs and those BMPs listed for construction related waste load allocations have also been incorporated.
<br />NAME OF WATER BODY
<br />TYPE (ditch, pond,
<br />wetland, lake, etc.)
<br />Special, Prohibited,
<br />Restricted Water
<br />Flows to Impaired
<br />Water Within 1-Mile 2
<br />USEPA Approved
<br />Construction Related
<br />TMDL3
<br />Rum River
<br />River
<br />Nutrients
<br />Yes
<br />NaN
<br />'Special, prohibited, and restricted waters are listed in Section 23 of the MN Construction Stormwater General Permit (MNR100001).
<br />2 Identified as impaired under section 303 (d) of the federal Clean Water Act for phosphorus, turbidity, TSS, dissolved oxygen, and/or aquatic biota.
<br />3 Construction Related TMDLs include those related to: phosphorus, turbidity, TSS, dissolved oxygen, and/or aquatic biota.
<br />IMPLEMENTATION SCHEDULE AND PHASING: The Contractor is required to provide an updated schedule and site management plan
<br />meeting the minimum requirements of Section 1717 of the Minnesota Standard Specifications for Construction.
<br />1) Submit SWPPP Updates to Engineer. Submittal shall include any requested changes to the SWPPP, including but not limited to:
<br />Trained Personnel, Locations for Stockpiles, Concrete Washout, Sanitation Facilities, Types and Locations of Erosion &
<br />Sediment Control. Failure to submit updates shall be considered acceptance of the SWPPP as designed with no changes.
<br />2) Install perimeter sediment control, inlet protection, and construction exit.
<br />3) Complete Site Grading.
<br />4) Add additional temporary BMPs as necessary during construction based on inspection reports.
<br />5) Ensure final stabilization measures are complete.
<br />6) Provide digital copy of all Field SWPPP Documentation including Inspection Reports and SWPPP Revisions to the Owner.
<br />7) Submit Notice of Termination (NOT) to MPCA. NOTE: The NOT must be submitted to MPCA before Final Stabilization is
<br />considered complete.
<br />I HEREBY CERTIFY THAT THIS PLAN, SPECIFICATION, OR REPORT WAS PREPARED
<br />BY ME OR UNDER MY DIRECT SUPERVMON AND THAT I AM A DULY LICENSED
<br />PROFESSIONAL ENGINEER UNDER THE LAWS OF THE STATE OF MINNESOTA
<br />Zw
<br />KEVIN P. KIELB
<br />uc No 23211 DATE 8/20/2024
<br />BOLTON
<br />& MENK
<br />7533 SU N WOOD DR NW, SUITE 206
<br />RAMSEY, MN 55303
<br />Phone: (763) 433-2851
<br />Email: Ramsey@bolton-menk.com
<br />www.bolton-menk.com
<br />DESIGNED ZFL
<br />NO
<br />ISSUED FOR
<br />DATE
<br />DRAWN TJH
<br />CITY OF RAMSEY, MINNESOTA
<br />CHECKED KPK
<br />RIVERS BEND REGIONAL STORMWATER IMPROVEMENTS
<br />CLIENTCP 25-01
<br />PRO1 NO
<br />STORM WATER POLLUTION PREVENTION PLAN
<br />SHEET
<br />8
<br />OF
<br />12