Funding for this improvement is proposed to come from Pavement Management Funds and Storm Water Utility <br />Funds. <br />On March 31, 2025 a total of ten (10) bids were received, opened, and tabulated, and the following bids were <br />found to comply with the advertisement for bids. <br />Contractor <br />Total Bid <br />Park Construction Company <br />$423,698.35 <br />Landall Services LLC <br />$430,310.25 <br />orth Valley, Inc. <br />$439,623.66 <br />Asphalt Surface Technologies Corp. <br />$452,700.86 <br />Douglas -Kerr Underground, LLC <br />$465,769.12 <br />GMH Asphalt Corporation <br />Forest Lake Contracting, Inc. <br />Bituminous Roadways, Inc. <br />orthwest <br />Diversified Paving <br />$479,754.23 <br />$533,065.00 <br />$548,616.50 <br />$575,149.99 <br />$710,188.08 <br />ngineer's Estimate <br />$598, 514.00 <br />The bid of Park Construction Company of Minneapolis, Minnesota, in the amount of $423,698.35 for the total bid <br />of said improvements in accordance with the approved plans and specifications and advertisement for bids, is the <br />lowest responsible bidder. Adding indirect costs in the amount of 23-percent brings the total project costs to <br />$521,148.97. <br />The low bid is 29-percent less than the engineer's estimate, primarily due to lower than anticipated bituminous <br />paving and concrete curb and gutter prices. <br />Funding Source Breakdown: <br />Funding Source <br />Construction Costs <br />Indirect Costs <br />Total Costs <br />Pavement Management <br />Funds <br />$363,521.15 <br />$83,609.86 <br />$447,131.01 <br />Storm Sewer Utility <br />Funds <br />$60,177.20 <br />$13,840.76 <br />$74,017.96 <br />Project Total <br />$423,698.35 <br />$97,450.62 <br />$521,148.97 <br />The CIP level estimate had a total estimated project cost of $642,890, which includes street costs of $559,035 and <br />storm sewer costs of $83,855. The final project costs may change depending upon final construction quantities. <br />Hakanson Anderson submitted a proposal for construction staking and as -built survey of the proposed <br />improvements for a total not -to -exceed amount of $8,000.00. The construction staking and as -built survey are <br />included in the indirect project costs. <br />City staff propose to administer and inspect construction. Plans and specifications were prepared in-house as part <br />of staff's normal duties. <br />Recommendation: <br />Staff recommends Alternative # 1. <br />Outcome/Action: <br />Motion to adopt Resolution #25-070 awarding a contract to Park Construction Company in the amount of <br />$423,698.35 for Sorteberg's Street Reconstructions, Improvement Project #25-06. <br />